ABR 1000 Tables#
The ABR1000 model is a cost model that estimates the cost of ABR1000. The model contains three main tables: account, cost element, and variable. The account table contains the main cost estimation for ABR1000 model. Each account is divided into three main cost categories: Factory Equipment Costs, Labor Costs, and Material Costs. The cost element table contains the cost element information for the ABR1000 model. Some cost element are calculated using algorithms, that need variables to calculate the cost. The variable table contains the variable information for the ABR1000 model. Each table is associated with a unique identifier, which is used to track and categorize costs. The tables are connected to each other through the different columns.
Note
The ABR1000 model only contains partial data for the account table, the total direct cost is calculated using COA 2C calculated direct cost and the total percentage of the known accounts.
ABR1000 Account Table#
This table contains the account information for the ABR1000 model. ABR1000 account table can also ordered by GNCOA. Each entity in the account table is associated with a unique identifier, which is used to track and categorize costs. The table is organized into multiple levels, with each level representing a different component or subtask.
The table includes the following columns:
ind: unique identifier for each account
code_of_account: code of account
account_description: description of the account
total_cost: total cost of the account unit in dollars
level: level of the account
supaccount: superior account
review_status: review status of the account, note that the default value should always be Unchanged
prn: percentage of the account cost in the total direct cost
gncoa: generalized nuclear code of account
gn_level: generalized nuclear code of account level
gn_supaccount: generalized nuclear code of account superior account
gn_ind: generalized nuclear code of account unique identifier
ind |
code_of_account |
account_description |
total_cost |
level |
supaccount |
review_status |
prn |
gncoa |
gn_level |
gn_supaccount |
gn_ind |
|---|---|---|---|---|---|---|---|---|---|---|---|
1 |
2 |
TOTAL DIRECT COST |
1419783854 |
0 |
Unchanged |
1 |
20 |
0 |
1 |
||
2 |
2C |
Calculated DIRECT COST |
1225489991 |
0 |
Unchanged |
0.863152505 |
2C |
0 |
2 |
||
3 |
211 |
Yardwork |
71213859.06 |
2 |
21 |
Unchanged |
0.027628981 |
211 |
2 |
21 |
3 |
4 |
212 |
Reactor containment building |
81425435.33 |
2 |
21 |
Unchanged |
0.071675596 |
212.1 |
3 |
212 |
4 |
5 |
213 |
Turbine room and heater bay |
24604390.8 |
2 |
21 |
Unchanged |
0.02559467 |
213.1 |
3 |
213 |
5 |
6 |
215 |
Primary auxiliary building and tunnels |
12470000 |
2 |
21 |
Unchanged |
0.020420772 |
214.2 |
3 |
214 |
8 |
7 |
216 |
Waste processing building |
38750000 |
2 |
21 |
Unchanged |
0.015882927 |
215 |
2 |
213 |
9 |
8 |
217 |
Fuel storage building |
28149583.82 |
2 |
21 |
Unchanged |
0.010921249 |
214.1 |
3 |
21 |
7 |
9 |
218A |
Control Room/Diesel Generator Building |
16250000 |
3 |
218 |
Unchanged |
0.020007875 |
213.21 |
3 |
214 |
6 |
10 |
220A.211 |
Vessel Structure (NSSS) |
137000000 |
3 |
220A |
Unchanged |
0.027158047 |
221.121 |
3 |
221 |
10 |
11 |
220A.2121 |
Lower Internals (NSSS) |
45204200 |
3 |
220A |
Unchanged |
0.012329754 |
221.131 |
3 |
221 |
11 |
12 |
220A.2122 |
Upper Internals (NSSS) |
45204200 |
3 |
220A |
Unchanged |
0.012329754 |
221.132 |
3 |
221 |
12 |
13 |
220A.2131 |
Control Rods (NSSS) |
1320000 |
3 |
220A |
Unchanged |
0.001202713 |
221.211 |
3 |
221 |
13 |
14 |
220A.2132 |
Control Rod Drives (NSSS) |
13453440 |
3 |
220A |
Unchanged |
0.013540226 |
221.212 |
3 |
221 |
14 |
15 |
220A.221 |
Main Coolant Pumps (NSSS) |
55696873.29 |
3 |
220A |
Unchanged |
0.048589625 |
222.11 |
3 |
222 |
16 |
16 |
220A.222 |
Reactor Coolant Piping (NSSS) |
7464800 |
3 |
220A |
Unchanged |
0.004422882 |
222.21 |
3 |
222 |
18 |
17 |
220A.223 |
Steam Generators (NSSS) |
122087095.9 |
3 |
220A |
Unchanged |
0.058118221 |
222.31 |
3 |
222 |
20 |
18 |
220A.224 |
Pressurizer (NSSS) |
1379368.421 |
3 |
220A |
Unchanged |
0.003220169 |
222.41 |
3 |
222 |
22 |
19 |
222 |
Main heat transfer transport system |
8220525.704 |
2 |
22 |
Unchanged |
0.010942603 |
222 |
2 |
222 |
15 |
20 |
222.11 |
Fluid Circulation Drive System (Field Cost 222) |
2504335.453 |
3 |
222 |
Unchanged |
0.003333601 |
222.12 |
3 |
222 |
17 |
21 |
222.12 |
Reactor Coolant Piping System (Field Cost 222) |
4924232.687 |
3 |
222 |
Unchanged |
0.006554803 |
222.22 |
3 |
22 |
19 |
22 |
222.13 |
Steam Generator Equipment (Field Cost 222) |
697187.7179 |
3 |
222 |
Unchanged |
0.000928049 |
222.32 |
3 |
222 |
21 |
23 |
222.14 |
Pressurizing System (Field Cost 222) |
94769.84553 |
3 |
222 |
Unchanged |
0.000126151 |
222.43 |
3 |
222 |
23 |
24 |
224 |
Radwaste processing |
59673441.34 |
2 |
22 |
Unchanged |
0.023151622 |
224 |
2 |
22 |
24 |
25 |
226.4 |
Coolant Treatment & Recycle |
34304867.39 |
3 |
226 |
Unchanged |
0.015817883 |
226.35 |
3 |
226 |
25 |
26 |
226.7 |
Aux Cool Sys (Broken Down Further) |
0 |
3 |
226 |
Unchanged |
0.021415357 |
226.7 |
3 |
226 |
26 |
27 |
227 |
Reactor instrumentation and control |
61419737.22 |
2 |
22 |
Unchanged |
0.023829136 |
227.2 |
3 |
227 |
27 |
28 |
231 |
Turbine generator |
57399816.35 |
2 |
23 |
Unchanged |
0.148118277 |
232.1 |
3 |
232 |
28 |
29 |
233 |
Condensing systems |
29065851.25 |
2 |
23 |
Unchanged |
0.032039296 |
233.21 |
3 |
23 |
30 |
30 |
234 |
Feedwater heating system |
0 |
2 |
23 |
Unchanged |
0.026077184 |
234 |
2 |
24 |
32 |
31 |
235 |
Other turbine plant equipment |
9563415.121 |
2 |
23 |
Unchanged |
0.024678068 |
232.2 |
3 |
233 |
29 |
32 |
241 |
Switchgear |
21904347.8 |
2 |
24 |
Unchanged |
0.013206497 |
241 |
2 |
24 |
33 |
33 |
242 |
Station service equipment |
36970984.98 |
2 |
24 |
Unchanged |
0.022290424 |
242 |
2 |
24 |
34 |
34 |
245 |
Electric structure and wiring contnr. |
40891698.73 |
2 |
24 |
Unchanged |
0.024654288 |
245 |
2 |
24 |
35 |
35 |
246 |
Power and control wiring |
37773534.79 |
2 |
24 |
Unchanged |
0.022774295 |
246 |
2 |
26 |
36 |
36 |
252 |
Air, water and steam service systems |
81851078.87 |
2 |
25 |
Unchanged |
0.031755924 |
262 |
2 |
233 |
37 |
37 |
262 |
Mechanical equipment |
44777444.42 |
2 |
26 |
Unchanged |
0.04935819 |
233.22 |
3 |
232 |
31 |
ABR1000 Cost Element Table#
This table contains the cost element information for the ABR1000 model. Each entitiy in the account table is divided into 3 main cost categories: Factory Equipment Costs, Labor Costs, and Material Costs. The cost element table is associated with a unique identifier, which is used to track and categorize costs. The table is connected to the account table through the account column, which links each cost element to a specific account. It is also connected to the variable table through the variables column, and the algorithm table through the alg_name column.
The table includes the following columns:
ind: unique identifier for each cost element
cost_element: cost element name
cost_2017: cost of the element in 2017 dollars
sup_cost_ele: superior cost element
alg_name: algorithm name
fun_unit: algorithm function output unit
variables: variables used in the algorithm
account: account associated with the cost element
algno: algorithm number in the algorithm table
updated: updated status of the cost element, 0 for unchanged and 1 for updated, note that the default value should always be 0
ind |
cost_element |
cost_2017 |
sup_cost_ele |
alg_name |
fun_unit |
variables |
account |
algno |
updated |
|---|---|---|---|---|---|---|---|---|---|
1 |
211_fac |
810015.17 |
21_fac |
esc_1987 |
million |
escalate_1987, ref_211_fac |
211 |
12 |
0 |
2 |
212_fac |
0 |
21_fac |
default_0 |
million |
N/A |
212 |
N/A |
0 |
3 |
213_fac |
660388.72 |
21_fac |
MWth_scale |
million |
c_213_fac, mwth, scale_0.8 |
213 |
8 |
0 |
4 |
215_fac |
2121224.73 |
21_fac |
NO_ALG |
million |
N/A |
215 |
N/A |
0 |
5 |
216_fac |
1756069.67 |
21_fac |
NO_ALG |
million |
N/A |
216 |
N/A |
0 |
6 |
217_fac |
2842399.83 |
21_fac |
NO_ALG |
million |
N/A |
217 |
N/A |
0 |
7 |
218A_fac |
1314294.08 |
218_fac |
NO_ALG |
million |
N/A |
218A |
N/A |
0 |
8 |
220A.211_fac |
127380000 |
220A_fac |
NO_ALG |
million |
N/A |
220A.211 |
N/A |
0 |
9 |
220A.2121_fac |
45204200 |
220A_fac |
unit_weights |
million |
c_zero, c_220A.2121_ss_weight |
220A.2121 |
5 |
0 |
10 |
220A.2122_fac |
45204200 |
220A_fac |
unit_weights |
million |
c_zero, c_220A.2122_ss_weight |
220A.2122 |
5 |
0 |
11 |
220A.2131_fac |
1320000 |
220A_fac |
unit_facility |
million |
no_of_cr, c_cr_per_unit_fac |
220A.2131 |
16 |
0 |
12 |
220A.2132_fac |
13453440 |
220A_fac |
unit_facility |
million |
no_of_crd, c_crd_per_unit_fac |
220A.2132 |
16 |
0 |
13 |
220A.221_fac |
55696873.29 |
220A_fac |
unit_facility |
million |
no_of_rcpump, c_pump_per_unit_fac |
220A.221 |
16 |
0 |
14 |
220A.222_fac |
7464800 |
220A_fac |
unit_weights |
million |
c_zero, c_220A.222_ss_weight |
220A.222 |
5 |
0 |
15 |
220A.223_fac |
118647119.77 |
220A_fac |
Sgsum |
million |
N/A |
220A.223 |
N/A |
0 |
16 |
220A.224_fac |
1379368.42 |
220A_fac |
MWth_lmfbrscale |
million |
r_78_220A224_fac, mwth, scale_1.0 |
220A.224 |
24 |
0 |
17 |
222.11_fac |
1101963.79 |
222_fac |
MWth_scale |
million |
c_222.11_fac, mwth, scale_1.0 |
222.11 |
8 |
0 |
18 |
222.12_fac |
1280778.06 |
222_fac |
MWth_scale |
million |
c_222.12_fac, mwth, scale_1.0 |
222.12 |
8 |
0 |
19 |
222.13_fac |
21900.68 |
222_fac |
MWth_scale |
million |
c_222.13_fac, mwth, scale_1.0 |
222.13 |
8 |
0 |
20 |
222.14_fac |
4380.14 |
222_fac |
MWth_scale |
million |
c_222.14_fac, mwth, scale_1.0 |
222.14 |
8 |
0 |
21 |
222_fac |
2409022.68 |
22_fac |
MWth_scale |
million |
c_222_fac, mwth, scale_1.0 |
222 |
8 |
0 |
22 |
224_fac |
46047915.43 |
22_fac |
esc_1987 |
million |
escalate_1987, ref_224_fac |
224 |
12 |
0 |
23 |
226.4_fac |
34304867.39 |
226_fac |
MWth_scale |
million |
r_78_226.4_fac, mwth, scale_1.0 |
226.4 |
8 |
0 |
24 |
226.7_fac |
0 |
226_fac |
default_0 |
million |
N/A |
226.7 |
14 |
0 |
25 |
227_fac |
37538349.96 |
22_fac |
esc_1987 |
million |
escalate_1987, ref_227_fac |
227 |
12 |
0 |
26 |
231_fac |
53544604.81 |
23_fac |
dev_factor_ref |
million |
c_turbine, scale_tur_231_fac, scale_1.0 |
231 |
10 |
0 |
27 |
233_fac |
19829554.55 |
23_fac |
MWreth_scale |
million |
c_233_fac, mwreth, scale_0.8 |
233 |
25 |
0 |
28 |
234_fac |
0 |
23_fac |
default_0 |
million |
N/A |
234 |
14 |
0 |
29 |
235_fac |
4788444.35 |
23_fac |
ptn_account |
million |
c_231_fac, prn_235_of_231_fac |
235 |
4 |
0 |
30 |
241_fac |
20635161.28 |
24_fac |
MWe_scale |
million |
c_241_fac, mwe, scale_0.4 |
241 |
17 |
0 |
31 |
242_fac |
33563126.13 |
24_fac |
MWe_scale |
million |
c_242_fac, mwe, scale_0.4 |
242 |
17 |
0 |
32 |
245_fac |
0 |
24_fac |
MWe_scale |
million |
c_245_fac, mwe, scale_0.4 |
245 |
17 |
0 |
33 |
246_fac |
2902733.98 |
24_fac |
MWe_scale |
million |
c_246_fac, mwe, scale_0.4 |
246 |
17 |
0 |
34 |
252_fac |
24869567.31 |
25_fac |
esc_1987 |
million |
escalate_1987, ref_252_fac |
252 |
12 |
0 |
35 |
262_fac |
30555532.85 |
26_fac |
MWreth_scale |
million |
c_262_fac, mwreth, scale_0.8 |
262 |
25 |
0 |
36 |
2c_fac |
736246154.62 |
NO_ALG |
million |
N/A |
2 |
N/A |
0 |
|
37 |
211_lab |
41328822.54 |
21_lab |
esc_1987 |
million |
escalate_1987, ref_211_lab |
211 |
12 |
0 |
38 |
212_lab |
43940775.98 |
21_lab |
containment |
million |
Tot_Labor_containment |
212 |
7 |
0 |
39 |
213_lab |
11873274.12 |
21_lab |
MWth_scale |
million |
c_213_lab, mwth, scale_0.8 |
213 |
8 |
0 |
40 |
215_lab |
7101615.96 |
21_lab |
NO_ALG |
million |
N/A |
215 |
N/A |
0 |
41 |
216_lab |
24337584.5 |
21_lab |
NO_ALG |
million |
N/A |
216 |
N/A |
0 |
42 |
217_lab |
12836637.9 |
21_lab |
NO_ALG |
million |
N/A |
217 |
N/A |
0 |
43 |
218A_lab |
10038481.64 |
218_lab |
NO_ALG |
million |
N/A |
218A |
N/A |
0 |
44 |
220A.211_lab |
8750000 |
220A_lab |
NO_ALG |
million |
N/A |
220A.211 |
N/A |
0 |
45 |
220A.2121_lab |
0 |
220A_lab |
default_0 |
million |
N/A |
220A.2121 |
14 |
0 |
46 |
220A.2122_lab |
0 |
220A_lab |
default_0 |
million |
N/A |
220A.2122 |
14 |
0 |
47 |
220A.2131_lab |
0 |
220A_lab |
default_0 |
million |
N/A |
220A.2131 |
14 |
0 |
48 |
220A.2132_lab |
0 |
220A_lab |
default_0 |
million |
N/A |
220A.2132 |
14 |
0 |
49 |
220A.221_lab |
0 |
220A_lab |
default_0 |
million |
N/A |
220A.221 |
14 |
0 |
50 |
220A.222_lab |
0 |
220A_lab |
default_0 |
million |
N/A |
220A.222 |
14 |
0 |
51 |
220A.223_lab |
3173085.99 |
220A_lab |
Sgsum |
million |
N/A |
220A.223 |
N/A |
0 |
52 |
220A.224_lab |
0 |
220A_lab |
default_0 |
million |
N/A |
220A.224 |
14 |
0 |
53 |
222.11_lab |
1274883.33 |
222_lab |
MWth_scale |
million |
c_222.11_lab, mwth, scale_1.0 |
222.11 |
8 |
0 |
54 |
222.12_lab |
3317279.46 |
222_lab |
MWth_scale |
million |
c_222.12_lab, mwth, scale_1.0 |
222.12 |
8 |
0 |
55 |
222.13_lab |
613897.3 |
222_lab |
MWth_scale |
million |
r_222.13_lab, mwth, scale_1.0 |
222.13 |
8 |
0 |
56 |
222.14_lab |
82172.71 |
222_lab |
MWth_scale |
million |
c_222.14_lab, mwth, scale_1.0 |
222.14 |
8 |
0 |
57 |
222_lab |
5288232.81 |
22_mat |
MWth_scale |
million |
c_222_lab, mwth, scale_1.0 |
222 |
8 |
0 |
58 |
224_lab |
11434348.55 |
22_lab |
esc_1987 |
million |
escalate_1987, ref_224_lab |
224 |
12 |
0 |
59 |
226.4_lab |
0 |
226_lab |
default_0 |
million |
N/A |
226.4 |
14 |
0 |
60 |
226.7_lab |
0 |
226_lab |
default_0 |
million |
N/A |
226.7 |
14 |
0 |
61 |
227_lab |
21960889.79 |
22_lab |
esc_1987 |
million |
escalate_1987, ref_227_lab |
227 |
12 |
0 |
62 |
231_lab |
588990.65 |
23_lab |
ptn_account |
million |
c_231_fac, prn_fac_231_lab |
231 |
4 |
0 |
63 |
233_lab |
8082642.16 |
23_lab |
MWreth_scale |
million |
c_233_lab, mwreth, scale_0.8 |
233 |
25 |
0 |
64 |
234_lab |
0 |
23_lab |
default_0 |
million |
N/A |
234 |
14 |
0 |
65 |
235_lab |
4258930.48 |
23_lab |
ptn_account |
million |
c_231_lab, prn_235_of_231_lab |
235 |
4 |
0 |
66 |
241_lab |
1107205.12 |
24_lab |
MWe_scale |
million |
c_241_lab, mwe, scale_0.4 |
241 |
17 |
0 |
67 |
242_lab |
2861071.44 |
24_lab |
MWe_scale |
million |
c_242_lab, mwe, scale_0.4 |
242 |
17 |
0 |
68 |
245_lab |
32970390.22 |
24_lab |
MWe_scale |
million |
c_245_lab, mwe, scale_0.4 |
245 |
17 |
0 |
69 |
246_lab |
21514837.92 |
24_lab |
MWe_scale |
million |
c_246_lab, mwe, scale_0.4 |
246 |
17 |
0 |
70 |
252_lab |
44371766.01 |
25_lab |
esc_1987 |
million |
escalate_1987, ref_252_lab |
252 |
12 |
0 |
71 |
262_lab |
12634376.8 |
26_lab |
MWreth_scale |
million |
c_262_lab, mwreth, scale_0.8 |
262 |
25 |
0 |
72 |
2c_lab |
330450874.57 |
NO_ALG |
million |
N/A |
2 |
N/A |
0 |
|
73 |
211_mat |
29075021.35 |
21_mat |
esc_1987 |
million |
escalate_1987, ref_211_mat |
211 |
12 |
0 |
74 |
212_mat |
37484659.34 |
21_mat |
containment |
million |
Tot_Mat_containment |
212 |
7 |
0 |
75 |
213_mat |
12070727.96 |
21_mat |
MWth_scale |
million |
c_213_mat, mwth, scale_0.8 |
213 |
8 |
0 |
76 |
215_mat |
3247159.31 |
21_mat |
NO_ALG |
million |
N/A |
215 |
N/A |
0 |
77 |
216_mat |
12656345.83 |
21_mat |
NO_ALG |
million |
N/A |
216 |
N/A |
0 |
78 |
217_mat |
12470546.09 |
21_mat |
NO_ALG |
million |
N/A |
217 |
N/A |
0 |
79 |
218A_mat |
4897224.28 |
218_mat |
NO_ALG |
million |
N/A |
218A |
N/A |
0 |
80 |
220A.211_mat |
870000 |
220A_mat |
NO_ALG |
million |
N/A |
220A.211 |
N/A |
0 |
81 |
220A.2121_mat |
0 |
220A_mat |
default_0 |
million |
N/A |
220A.2121 |
14 |
0 |
82 |
220A.2122_mat |
0 |
220A_mat |
default_0 |
million |
N/A |
220A.2122 |
14 |
0 |
83 |
220A.2131_mat |
0 |
220A_mat |
default_0 |
million |
N/A |
220A.2131 |
14 |
0 |
84 |
220A.2132_mat |
0 |
220A_mat |
default_0 |
million |
N/A |
220A.2132 |
14 |
0 |
85 |
220A.221_mat |
0 |
220A_mat |
default_0 |
million |
N/A |
220A.221 |
14 |
0 |
86 |
220A.222_mat |
0 |
220A_mat |
default_0 |
million |
N/A |
220A.222 |
14 |
0 |
87 |
220A.223_mat |
266890.16 |
220A_mat |
Sgsum |
million |
N/A |
220A.223 |
N/A |
0 |
88 |
220A.224_mat |
0 |
220A_mat |
default_0 |
million |
N/A |
220A.224 |
14 |
0 |
89 |
222.11_mat |
127488.33 |
222_mat |
MWth_scale |
million |
c_222.11_mat, mwth, scale_1.0 |
222.11 |
8 |
0 |
90 |
222.12_mat |
326175.16 |
222_mat |
MWth_scale |
million |
c_222.12_mat, mwth, scale_1.0 |
222.12 |
8 |
0 |
91 |
222.13_mat |
61389.73 |
222_mat |
MWth_scale |
million |
r_222.13_mat, mwth, scale_1.0 |
222.13 |
8 |
0 |
92 |
222.14_mat |
8217 |
222_mat |
MWth_scale |
million |
c_222.14_mat, mwth, scale_1.0 |
222.14 |
8 |
0 |
93 |
222_mat |
523270.22 |
22_mat |
MWth_scale |
million |
c_222_mat, mwth, scale_1.0 |
222 |
8 |
0 |
94 |
224_mat |
2191177.36 |
22_mat |
esc_1987 |
million |
escalate_1987, ref_224_mat |
224 |
12 |
0 |
95 |
226.4_mat |
0 |
226_mat |
default_0 |
million |
N/A |
226.4 |
14 |
0 |
96 |
226.7_mat |
0 |
226_mat |
default_0 |
million |
N/A |
226.7 |
14 |
0 |
97 |
227_mat |
1920497.47 |
22_mat |
esc_1987 |
million |
escalate_1987, ref_227_mat |
227 |
12 |
0 |
98 |
231_mat |
3266220.89 |
23_mat |
ptn_account |
million |
c_231_fac, prn_fac_231_mat |
231 |
4 |
0 |
99 |
233_mat |
1153654.54 |
23_mat |
MWreth_scale |
million |
c_233_mat, mwreth, scale_0.8 |
233 |
25 |
0 |
100 |
234_mat |
0 |
23_mat |
default_0 |
million |
N/A |
234 |
14 |
0 |
101 |
235_mat |
516040.29 |
23_mat |
ptn_account |
million |
c_231_mat, prn_235_of_231_mat |
235 |
4 |
0 |
102 |
241_mat |
161981.4 |
24_mat |
MWe_scale |
million |
c_241_mat, mwe, scale_0.4 |
241 |
17 |
0 |
103 |
242_mat |
546787.41 |
24_mat |
MWe_scale |
million |
c_242_mat, mwe, scale_0.4 |
242 |
17 |
0 |
104 |
245_mat |
7921308.52 |
24_mat |
MWe_scale |
million |
c_245_mat, mwe, scale_0.4 |
245 |
17 |
0 |
105 |
246_mat |
13355962.89 |
24_mat |
MWe_scale |
million |
c_246_mat, mwe, scale_0.4 |
246 |
17 |
0 |
106 |
252_mat |
12609745.55 |
25_mat |
esc_1987 |
million |
escalate_1987, ref_252_mat |
252 |
12 |
0 |
107 |
262_mat |
1587534.77 |
26_mat |
MWreth_scale |
million |
c_262_mat, mwreth, scale_0.8 |
262 |
25 |
0 |
108 |
2c_mat |
158795865.48 |
NO_ALG |
million |
N/A |
2 |
N/A |
0 |
ABR1000 Variable Table#
This table contains the variable information for the ABR1000 model. All variables are needed to be calculated by the algorithm. Some variables are connected to the algorithm table through the var_alg column, which links each variable to a specific algorithm. The table is also connected to itself through the v_linked and var_needed column, which links each variable to a superior variable and the variables needed to calculate it.
The table includes the following columns:
ind: unique identifier for each variable
var_name: variable name
var_description: description of the variable
var_value: value of the variable
var_unit: unit of the variable
var_alg: algorithm associated with the variable if any
var_need: variables needed to calculate the variable if any
v_linked: superior variable if any
user_input: user input status of the variable, 0 for not user input and 1 for user input, note that the default value should always be 0
ind |
var_name |
var_description |
var_value |
var_unit |
var_alg |
var_need |
v_linked |
user_input |
|---|---|---|---|---|---|---|---|---|
1 |
c_213_fac |
Turbine building structure factory cost |
1.7706643 |
million |
NULL |
NULL |
NULL |
0 |
2 |
c_213_lab |
Turbine building structure labor cost |
31.835162 |
million |
NULL |
NULL |
NULL |
0 |
3 |
c_213_mat |
Turbine building structure material cost |
32.364585 |
million |
NULL |
NULL |
NULL |
0 |
4 |
c_220A.2121_ss_weight |
weight of the stainless steel lower internals |
145.82 |
ton |
NULL |
NULL |
NULL |
0 |
5 |
c_220A.2122_ss_weight |
weight of the stainless steel upper internals |
145.82 |
ton |
NULL |
NULL |
NULL |
0 |
6 |
c_220A.222_ss_weight |
weight of the stainless steel reactor coolant piping |
24.08 |
ton |
NULL |
NULL |
NULL |
0 |
7 |
c_222_fac |
Main heat transfer transport system factory cost |
8.265356805 |
million |
NULL |
NULL |
NULL |
0 |
8 |
c_222_lab |
Main heat transfer transport system labor cost |
18.14392675 |
million |
NULL |
NULL |
NULL |
0 |
9 |
c_222_mat |
Main heat transfer transport system material cost |
1.795340116 |
million |
NULL |
NULL |
NULL |
0 |
10 |
c_222.11_fac |
Fluid Circulation Drive System (Field Cost 222) factory cost |
3.780837782 |
million |
NULL |
NULL |
NULL |
0 |
11 |
c_222.11_lab |
Fluid Circulation Drive System (Field Cost 222) labor cost |
4.374124686 |
million |
NULL |
NULL |
NULL |
0 |
12 |
c_222.11_mat |
Fluid Circulation Drive System (Field Cost 222) material cost |
0.437412469 |
million |
NULL |
NULL |
NULL |
0 |
13 |
c_222.12_fac |
Reactor Coolant Piping System (Field Cost 222) factory cost |
4.394349539 |
million |
NULL |
NULL |
NULL |
0 |
14 |
c_222.12_lab |
Reactor Coolant Piping System (Field Cost 222) labor cost |
11.38158584 |
million |
NULL |
NULL |
NULL |
0 |
15 |
c_222.12_mat |
Reactor Coolant Piping System (Field Cost 222) material cost |
1.119106974 |
million |
NULL |
NULL |
NULL |
0 |
16 |
c_222.13_fac |
Steam Generator Equipment (Field Cost 222) factory cost |
0.7514124 |
million |
NULL |
NULL |
NULL |
0 |
17 |
c_222.14_fac |
Pressurizing System (Field Cost 222) factory cost |
0.015028247 |
million |
NULL |
NULL |
NULL |
0 |
18 |
c_222.14_lab |
Pressurizing System (Field Cost 222) labor cost |
0.281934576 |
million |
NULL |
NULL |
NULL |
0 |
19 |
c_222.14_mat |
Pressurizing System (Field Cost 222) material cost |
0.028192508 |
million |
NULL |
NULL |
NULL |
0 |
20 |
c_231_fac |
Turbine factory cost |
53.54460481 |
million |
NULL |
NULL |
NULL |
0 |
21 |
c_231_lab |
Turbine labor cost |
0.588990653 |
million |
NULL |
NULL |
NULL |
0 |
22 |
c_231_mat |
Turbine material cost |
3.26622089 |
million |
NULL |
NULL |
NULL |
0 |
23 |
c_233_fac |
Condensing Systems factory cost |
56.339442 |
million |
NULL |
NULL |
NULL |
0 |
24 |
c_233_lab |
Condensing Systems labor cost |
22.964285 |
million |
NULL |
NULL |
NULL |
0 |
25 |
c_233_mat |
Condensing Systems material cost |
3.2777465 |
million |
NULL |
NULL |
NULL |
0 |
26 |
c_241_fac |
Switchgear factory cost |
32.06748045 |
million |
NULL |
NULL |
NULL |
0 |
27 |
c_241_lab |
Switchgear labor cost |
1.720620353 |
million |
NULL |
NULL |
NULL |
0 |
28 |
c_241_mat |
Switchgear material cost |
0.251722551 |
million |
NULL |
NULL |
NULL |
0 |
29 |
c_242_fac |
Station service equipment factory cost |
52.15781338 |
million |
NULL |
NULL |
NULL |
0 |
30 |
c_242_lab |
Station service equipment labor cost |
4.446166005 |
million |
NULL |
NULL |
NULL |
0 |
31 |
c_242_mat |
Station service equipment material cost |
0.849719287 |
million |
NULL |
NULL |
NULL |
0 |
32 |
c_245_fac |
Electric structure and wiring contnr. factory cost |
0 |
million |
NULL |
NULL |
NULL |
0 |
33 |
c_245_lab |
Electric structure and wiring contnr. labor cost |
51.23668914 |
million |
NULL |
NULL |
NULL |
0 |
34 |
c_245_mat |
Electric structure and wiring contnr. material cost |
12.30988227 |
million |
NULL |
NULL |
NULL |
0 |
35 |
c_246_fac |
Power and control wiring factory cost |
4.510910469 |
million |
NULL |
NULL |
NULL |
0 |
36 |
c_246_lab |
Power and control wiring labor cost |
33.4345167 |
million |
NULL |
NULL |
NULL |
0 |
37 |
c_246_mat |
Power and control wiring material cost |
20.75545101 |
million |
NULL |
NULL |
NULL |
0 |
38 |
c_262_fac |
Heat Rejection System factory cost |
86.81393498 |
million |
NULL |
NULL |
NULL |
0 |
39 |
c_262_lab |
Heat Rejection System labor cost |
35.89660737 |
million |
NULL |
NULL |
NULL |
0 |
40 |
c_262_mat |
Heat Rejection System material cost |
4.510480683 |
million |
NULL |
NULL |
NULL |
0 |
41 |
c_cr_per_unit_fac |
unit cost of rod |
0.06 |
million |
NULL |
NULL |
NULL |
0 |
42 |
c_crd_per_unit_fac |
unit cost of rod drive |
0.61152 |
million |
NULL |
NULL |
NULL |
0 |
43 |
c_pump_ap1000 |
AP1000 factory cost of main coolant pumps |
31.25 |
million |
NULL |
NULL |
c_pump_per_unit_fac |
0 |
44 |
c_pump_per_unit_fac |
Reactor coolant pumps Factory Equipment Cost |
13.92421832 |
million |
pump |
c_pump_ap1000,CH_abr1000,CH_AP1000,scale_0.52 |
NULL |
0 |
45 |
c_turbine |
Turbine equipment cost |
52.64956225 |
million |
NULL |
NULL |
NULL |
0 |
46 |
c_zero |
place holder for weight |
0 |
ton |
NULL |
NULL |
NULL |
0 |
47 |
CH_abr1000 |
CH factor of PWR-12 BE |
6072830 |
gpm*feet |
NULL |
NULL |
c_pump_per_unit_fac |
0 |
48 |
CH_AP1000 |
CH factor of AP1000 |
28743750 |
gpm*feet |
NULL |
NULL |
c_pump_per_unit_fac |
0 |
49 |
escalate_1987 |
escalator 1987 to 2017 |
2.849407 |
1 |
NULL |
NULL |
NULL |
0 |
50 |
mwe |
user_input MWE |
NULL |
MW |
NULL |
NULL |
NULL |
0 |
51 |
mwreth |
rejected thermal power |
620 |
MW |
NULL |
NULL |
NULL |
0 |
52 |
mwth |
user_input mwth |
NULL |
MW |
NULL |
NULL |
NULL |
0 |
53 |
no_of_cr |
Total control rods |
22 |
1 |
NULL |
NULL |
NULL |
0 |
54 |
no_of_crd |
Total control rod drives |
22 |
1 |
NULL |
NULL |
NULL |
0 |
55 |
no_of_rcpump |
total number of reactor coolant pumps |
4 |
1 |
NULL |
NULL |
NULL |
0 |
56 |
prn_235_of_231_fac |
factory portion of cost from factory of 231 |
0.089454842 |
1 |
NULL |
NULL |
NULL |
0 |
57 |
prn_235_of_231_lab |
labor portion of cost from labor of 231 |
1.302615598 |
1 |
NULL |
NULL |
NULL |
0 |
58 |
prn_235_of_231_mat |
material portion of cost from labor of 231 |
0.858473379 |
1 |
NULL |
NULL |
NULL |
0 |
59 |
prn_fac_231_lab |
labor portion of cost from factory of 231 |
0.061 |
1 |
NULL |
NULL |
NULL |
0 |
60 |
prn_fac_231_mat |
material portion of cost from factory of 231 |
0.0112 |
1 |
NULL |
NULL |
NULL |
0 |
61 |
r_222.13_lab |
labor cost of Steam Generator Equipment (Field Cost 222) |
2.10628 |
million |
NULL |
NULL |
NULL |
0 |
62 |
r_222.13_mat |
material cost of Steam Generator Equipment (Field Cost 222) |
0.210628 |
million |
NULL |
NULL |
NULL |
0 |
63 |
r_78_220A224_fac |
factory cost of pressurizer in ref |
5.2416 |
million |
NULL |
NULL |
NULL |
0 |
64 |
r_78_226.4_fac |
Coolant Treatment & Recycle factory cost |
117.7 |
million |
NULL |
NULL |
NULL |
0 |
65 |
ref_211_fac |
yardwork factory cost |
0.284275 |
million |
NULL |
NULL |
NULL |
0 |
66 |
ref_211_lab |
yardwork labor cost |
14.504359 |
million |
NULL |
NULL |
NULL |
0 |
67 |
ref_211_mat |
yardwork material cost |
10.203885 |
million |
NULL |
NULL |
NULL |
0 |
68 |
ref_224_fac |
Radwaste processing factory cost |
16.16052583 |
million |
NULL |
NULL |
NULL |
0 |
69 |
ref_224_lab |
Radwaste processing labor cost |
4.012887083 |
million |
NULL |
NULL |
NULL |
0 |
70 |
ref_224_mat |
Radwaste processing material cost |
0.768994167 |
million |
NULL |
NULL |
NULL |
0 |
71 |
ref_227_fac |
Reactor instrumentation and control factory cost |
13.174092 |
million |
NULL |
NULL |
NULL |
0 |
72 |
ref_227_lab |
Reactor instrumentation and control labor cost |
7.707179 |
million |
NULL |
NULL |
NULL |
0 |
73 |
ref_227_mat |
Reactor instrumentation and control material cost |
0.673999 |
million |
NULL |
NULL |
NULL |
0 |
74 |
ref_252_fac |
Air, water and steam service systems factory cost |
8.72798 |
million |
NULL |
NULL |
NULL |
0 |
75 |
ref_252_lab |
Air, water and steam service systems labor cost |
15.572281 |
million |
NULL |
NULL |
NULL |
0 |
76 |
ref_252_mat |
Air, water and steam service systems material cost |
4.425393 |
million |
NULL |
NULL |
NULL |
0 |
77 |
scale_0.4 |
electric scale 0.4 |
0.4 |
1 |
NULL |
NULL |
NULL |
0 |
78 |
scale_0.52 |
SH scale 1.0 |
0.52 |
1 |
NULL |
NULL |
c_pump_per_unit_fac |
0 |
79 |
scale_0.8 |
thermal scale 0.8 |
0.8 |
1 |
NULL |
NULL |
NULL |
0 |
80 |
scale_1.0 |
thermal scale 1.0 |
1 |
1 |
NULL |
NULL |
NULL |
0 |
81 |
scale_tur_231_fac |
factory scale of cost from turbine |
1.017 |
1 |
NULL |
NULL |
NULL |
0 |
82 |
CPI |
The Consumer Price Index |
2.2 |
1 |
NULL |
NULL |
infl |
0 |
83 |
Void_fraction |
Void fraction of the inside of the containment |
0.917 |
1 |
NULL |
NULL |
Internal_v_m3 |
0 |
84 |
liner_fraction |
liner fraction of containment |
1 |
1 |
NULL |
NULL |
Liner_s_m2 |
0 |
85 |
Cont_H_tot_m |
Containment total height |
50.5968 |
m |
NULL |
NULL |
Cont_H_wall_m |
0 |
86 |
Cont_rad_out_m |
Containment outside radius |
15.24 |
m |
NULL |
NULL |
Cont_H_wall_m,Cont_rad_in_m,Basemat_s_m2,Walls_s_m2,Walls_v_m3,Dome_rad_in_m,Dome_s_m2,Dome_v_m3,Surf_paint_m2 |
0 |
87 |
Cont_shell_t_m |
Shell wall thickness |
1.3716 |
m |
NULL |
NULL |
Cont_rad_in_m |
0 |
88 |
Cont_H_wall_m |
Containment wall height |
35.3568 |
m |
wall_height |
Cont_H_tot_m,Cont_rad_out_m |
Walls_s_m2,Walls_v_m3,Intern_tot_v_m3,Inside_liner_s,Surf_paint_m2 |
0 |
89 |
Basemat_t_m |
Basemat thickness |
3.048 |
m |
NULL |
NULL |
Basemat_v_m3 |
0 |
90 |
Dome_t_m |
Dome thickness |
1.0668 |
m |
NULL |
NULL |
Dome_rad_in_m |
0 |
91 |
Intern_wall_t |
Internal wall average thickness |
1.2192 |
m |
NULL |
NULL |
Internal_s_m2 |
0 |
92 |
React_cav_A_m2 |
Reactor cavity area |
1021.93344 |
m^2 |
NULL |
NULL |
Total_Labor_React_cav_liner,Total_Mat_React_cav_liner |
0 |
93 |
Cont_rad_in_m |
Containment inside radius |
13.8684 |
m |
inside_rad |
Cont_rad_out_m,Cont_shell_t_m |
Walls_s_m2,Walls_v_m3,Intern_tot_v_m3,Inside_liner_s |
0 |
94 |
Basemat_s_m2 |
Basemat surface |
729.6587699 |
m^2 |
round_surface |
Cont_rad_out_m |
Basemat_v_m3,Total_Labor_Constr_joints_Substr,Total_Labor_Formwork_Substr,Total_Labor_Waterproofing_Substr,Total_Labor_Welded_wire_fabric_Substr,Total_Mat_Constr_joints_Substr,Total_Mat_Formwork_Substr,Total_Mat_Waterproofing_Substr,Total_Mat_Welded_wire_fabric_Substr |
0 |
95 |
Basemat_v_m3 |
Basemat volume |
2223.999931 |
m^3 |
basemat_volume |
Basemat_s_m2,Basemat_t_m |
Struct_v_m3,Total_Labor_Cadweld_Substr,Total_Labor_Concrete_Substr,Total_Labor_Embedded_steel_Substr,Total_Labor_Reinforc_steel_Substr,Total_Mat_Cadweld_Substr,Total_Mat_Concrete_Substr,Total_Mat_Embedded_steel_Substr,Total_Mat_Reinforc_steel_Substr |
0 |
96 |
Walls_s_m2 |
Walls surface |
6466.527882 |
m^2 |
walls_surface |
Cont_H_wall_m,Cont_rad_out_m,Cont_rad_in_m |
Total_Labor_Constr_joints_Superstr,Total_Labor_Formwork_Superstr,Total_Labor_Rubbing_surfaces_Superstr,Total_Labor_Waterproofing_Superstr,Total_Mat_Constr_joints_Superstr,Total_Mat_Formwork_Superstr,Total_Mat_Rubbing_surfaces_Superstr,Total_Mat_Waterproofing_Superstr |
0 |
97 |
Walls_v_m3 |
Walls volume |
4434.744822 |
m^3 |
wall_volume |
Cont_H_wall_m,Cont_rad_out_m,Cont_rad_in_m |
Struct_v_m3,Total_Labor_Cadweld_Superstr,Total_Labor_Concrete_Superstr,Total_Labor_Embedded_steel_Superstr,Total_Labor_Reinforc_steel_Superstr,Total_Mat_Cadweld_Superstr,Total_Mat_Concrete_Superstr,Total_Mat_Embedded_steel_Superstr,Total_Mat_Reinforc_steel_Superstr |
0 |
98 |
Dome_rad_in_m |
Dome inside radius |
14.1732 |
m |
inside_rad |
Cont_rad_out_m,Dome_t_m |
Dome_s_m2,Dome_v_m3,Intern_tot_v_m3,Inside_liner_s |
0 |
99 |
Dome_s_m2 |
Roof surface |
2721.48128 |
m^2 |
roof_surface |
Cont_rad_out_m,Dome_rad_in_m |
Total_Labor_Constr_joints_Dome,Total_Labor_Formwork_Dome,Total_Labor_Rubbing_surfaces_Dome,Total_Labor_Waterproofing_Dome,Total_Mat_Constr_joints_Dome,Total_Mat_Formwork_Dome,Total_Mat_Rubbing_surfaces_Dome,Total_Mat_Waterproofing_Dome |
0 |
100 |
Dome_v_m3 |
Roof volume |
1450.366728 |
m^3 |
roof_volume |
Cont_rad_out_m,Dome_rad_in_m |
Struct_v_m3,Total_Labor_Cadweld_Dome,Total_Labor_Concrete_Dome,Total_Labor_Embedded_steel_Dome,Total_Labor_Reinforc_steel_Dome,Total_Mat_Cadweld_Dome,Total_Mat_Concrete_Dome,Total_Mat_Embedded_steel_Dome,Total_Mat_Reinforc_steel_Dome |
0 |
101 |
Intern_tot_v_m3 |
Tot intenal Volume |
27326.62075 |
m^3 |
tot_internal_volume |
Cont_rad_in_m,Cont_H_wall_m,Dome_rad_in_m |
Internal_v_m3,Total_Labor_Lighting_Power,Total_Labor_Plumb_drains,Total_Labor_Special_HVAC,Total_Labor_other,Total_Labor_fl_grate_handrail_stairs,Total_Mat_Lighting_Power,Total_Mat_Plumb_drains,Total_Mat_Special_HVAC,Total_Mat_other,Total_Mat_fl_grate_handrail_stairs |
0 |
102 |
Internal_v_m3 |
Building internal volume |
2268.109522 |
m^3 |
building_internal_volume |
Intern_tot_v_m3,Void_fraction |
Internal_s_m2,Struct_v_m3,Total_Labor_Cadweld_Interior,Total_Labor_Concrete_Interior,Total_Labor_Embedded_steel_Interior,Total_Labor_Maj_supp_embedments_Interior,Total_Labor_Reinforc_steel_Interior,Total_Mat_Cadweld_Interior,Total_Mat_Concrete_Interior,Total_Mat_Embedded_steel_Interior,Total_Mat_Maj_supp_embedments_Interior,Total_Mat_Reinforc_steel_Interior |
0 |
103 |
Internal_s_m2 |
Building internal surface |
3720.652103 |
m^2 |
building_internal _surface |
Internal_v_m3,Intern_wall_t |
Surf_paint_m2,Total_Labor_Constr_joints_Interior,Total_Labor_Formwork_Interior,Total_Labor_Rubbing_surfaces_Interior,Total_Mat_Constr_joints_Interior,Total_Mat_Formwork_Interior,Total_Mat_Rubbing_surfaces_Interior |
0 |
104 |
Struct_v_m3 |
volume of the structures |
10377.221 |
m^3 |
volume_of_the_structures |
Basemat_v_m3,Walls_v_m3,Dome_v_m3,Internal_v_m3 |
Total_Labor_Misc_steel_frames,Total_Labor_Struct_steel,Total_Mat_Misc_steel_frames,Total_Mat_Struct_steel |
0 |
105 |
Inside_liner_s |
Inside liner surface |
4947.305358 |
m^2 |
Inside_liner_surface |
Cont_rad_in_m,Cont_H_wall_m,Dome_rad_in_m |
Liner_s_m2,Surf_paint_m2, |
0 |
106 |
Liner_s_m2 |
Liner Surface |
4947.305358 |
m^2 |
liner_Surface |
Inside_liner_s,liner_fraction |
Total_Labor_cont_liner,Total_Mat_cont_liner |
0 |
107 |
Surf_paint_m2 |
painted surface |
13512.89169 |
m^2 |
painted_surface |
Inside_liner_s,Cont_H_wall_m,Cont_rad_out_m,Internal_s_m2 |
Total_Labor_painting,Total_Mat_painting |
0 |
108 |
infl |
Inflation rate |
2.870501004 |
1 |
Inflation_rate |
CPI |
Unit_Labor_Cadweld_Substr,Unit_Labor_Cadweld_Superstr,Unit_Labor_Cadweld_Dome,Unit_Labor_Cadweld_Interior,Unit_Labor_Concrete_Substr,Unit_Labor_Concrete_Superstr,Unit_Labor_Concrete_Dome,Unit_Labor_Concrete_Interior,Unit_Labor_Constr_joints_Substr,Unit_Labor_Constr_joints_Superstr,Unit_Labor_Constr_joints_Dome,Unit_Labor_Constr_joints_Interior,Unit_Labor_Embedded_steel_Substr,Unit_Labor_Embedded_steel_Superstr,Unit_Labor_Embedded_steel_Dome,Unit_Labor_Embedded_steel_Interior,Unit_Labor_Formwork_Substr,Unit_Labor_Formwork_Superstr,Unit_Labor_Formwork_Dome,Unit_Labor_Formwork_Interior,Unit_Labor_Maj_supp_embedments_Interior,Unit_Labor_Reinforc_steel_Substr,Unit_Labor_Reinforc_steel_Superstr,Unit_Labor_Reinforc_steel_Dome,Unit_Labor_Reinforc_steel_Interior,Unit_Labor_Rubbing_surfaces_Superstr,Unit_Labor_Rubbing_surfaces_Dome,Unit_Labor_Rubbing_surfaces_Interior,Unit_Labor_Waterproofing_Substr,Unit_Labor_Waterproofing_Superstr,Unit_Labor_Waterproofing_Dome,Unit_Labor_Welded_wire_fabric_Substr,Unit_Labor_Lighting_Power,Unit_Labor_Plumb_drains,Unit_Labor_Special_HVAC,Unit_Labor_other,Unit_Labor_Misc_steel_frames,Unit_Labor_React_cav_liner,Unit_Labor_Struct_steel,Unit_Labor_cont_liner,Unit_Labor_fl_grate_handrail_stairs,Unit_Labor_painting,Unit_Mat_Cadweld_Substr,Unit_Mat_Cadweld_Superstr,Unit_Mat_Cadweld_Dome,Unit_Mat_Cadweld_Interior,Unit_Mat_Concrete_Substr,Unit_Mat_Concrete_Superstr,Unit_Mat_Concrete_Dome,Unit_Mat_Concrete_Interior,Unit_Mat_Constr_joints_Substr,Unit_Mat_Constr_joints_Superstr,Unit_Mat_Constr_joints_Dome,Unit_Mat_Constr_joints_Interior,Unit_Mat_Embedded_steel_Substr,Unit_Mat_Embedded_steel_Superstr,Unit_Mat_Embedded_steel_Dome,Unit_Mat_Embedded_steel_Interior,Unit_Mat_Formwork_Substr,Unit_Mat_Formwork_Superstr,Unit_Mat_Formwork_Dome,Unit_Mat_Formwork_Interior,Unit_Mat_Maj_supp_embedments_Interior,Unit_Mat_Reinforc_steel_Substr,Unit_Mat_Reinforc_steel_Superstr,Unit_Mat_Reinforc_steel_Dome,Unit_Mat_Reinforc_steel_Interior,Unit_Mat_Rubbing_surfaces_Superstr,Unit_Mat_Rubbing_surfaces_Dome,Unit_Mat_Rubbing_surfaces_Interior,Unit_Mat_Waterproofing_Substr,Unit_Mat_Waterproofing_Superstr,Unit_Mat_Waterproofing_Dome,Unit_Mat_Welded_wire_fabric_Substr,Unit_Mat_Lighting_Power,Unit_Mat_Plumb_drains,Unit_Mat_Special_HVAC,Unit_Mat_other,Unit_Mat_Misc_steel_frames,Unit_Mat_React_cav_liner,Unit_Mat_Struct_steel,Unit_Mat_cont_liner,Unit_Mat_fl_grate_handrail_stairs,Unit_Mat_painting |
0 |
109 |
Unit_EEDB_Labor_Cadweld_Substr |
Unit cost of Labor Cadweld Substructure (base mat) in EEDB |
85.46 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Cadweld_Substr |
0 |
110 |
Unit_EEDB_Labor_Cadweld_Superstr |
Unit cost of Labor Cadweld Superstructure (shell) in EEDB |
114.62 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Cadweld_Superstr |
0 |
111 |
Unit_EEDB_Labor_Cadweld_Dome |
Unit cost of Labor Cadweld Superstructure (dome) in EEDB |
231.09 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Cadweld_Dome |
0 |
112 |
Unit_EEDB_Labor_Cadweld_Interior |
Unit cost of Labor Cadweld Interior structure in EEDB |
48.2 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Cadweld_Interior |
0 |
113 |
Unit_EEDB_Labor_Concrete_Substr |
Unit cost of Labor Concrete Substructure (base mat) in EEDB |
72.52 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Concrete_Substr |
0 |
114 |
Unit_EEDB_Labor_Concrete_Superstr |
Unit cost of Labor Concrete Superstructure (shell) in EEDB |
87.39 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Concrete_Superstr |
0 |
115 |
Unit_EEDB_Labor_Concrete_Dome |
Unit cost of Labor Concrete Superstructure (dome) in EEDB |
78.02 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Concrete_Dome |
0 |
116 |
Unit_EEDB_Labor_Concrete_Interior |
Unit cost of Labor Concrete Interior structure in EEDB |
97.57 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Concrete_Interior |
0 |
117 |
Unit_EEDB_Labor_Constr_joints_Substr |
Unit cost of Labor Construction joints Substructure (base mat) in EEDB |
14.51 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Constr_joints_Substr |
0 |
118 |
Unit_EEDB_Labor_Constr_joints_Superstr |
Unit cost of Labor Construction joints Superstructure (shell) in EEDB |
12.44 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Constr_joints_Superstr |
0 |
119 |
Unit_EEDB_Labor_Constr_joints_Dome |
Unit cost of Labor Construction joints Superstructure (dome) in EEDB |
4.75 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Constr_joints_Dome |
0 |
120 |
Unit_EEDB_Labor_Constr_joints_Interior |
Unit cost of Labor Construction joints Interior structure in EEDB |
2.05 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Constr_joints_Interior |
0 |
121 |
Unit_EEDB_Labor_Embedded_steel_Substr |
Unit cost of Labor Embedded steel Substructure (base mat) in EEDB |
3.98 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Embedded_steel_Substr |
0 |
122 |
Unit_EEDB_Labor_Embedded_steel_Superstr |
Unit cost of Labor Embedded steel Superstructure (shell) in EEDB |
15.98 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Embedded_steel_Superstr |
0 |
123 |
Unit_EEDB_Labor_Embedded_steel_Dome |
Unit cost of Labor Embedded steel Superstructure (dome) in EEDB |
0 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Embedded_steel_Dome |
0 |
124 |
Unit_EEDB_Labor_Embedded_steel_Interior |
Unit cost of Labor Embedded steel Interior structure in EEDB |
337.14 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Embedded_steel_Interior |
0 |
125 |
Unit_EEDB_Labor_Formwork_Substr |
Unit cost of Labor Formwork Substructure (base mat) in EEDB |
93.11 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Formwork_Substr |
0 |
126 |
Unit_EEDB_Labor_Formwork_Superstr |
Unit cost of Labor Formwork Superstructure (shell) in EEDB |
109.83 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Formwork_Superstr |
0 |
127 |
Unit_EEDB_Labor_Formwork_Dome |
Unit cost of Labor Formwork Superstructure (dome) in EEDB |
58.66 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Formwork_Dome |
0 |
128 |
Unit_EEDB_Labor_Formwork_Interior |
Unit cost of Labor Formwork Interior structure in EEDB |
231.52 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Formwork_Interior |
0 |
129 |
Unit_EEDB_Labor_Maj_supp_embedments_Interior |
Unit cost of Labor Major Support Embedments Interior structure in EEDB |
153.53 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Maj_supp_embedments_Interior |
0 |
130 |
Unit_EEDB_Labor_Reinforc_steel_Substr |
Unit cost of Labor Reinforc steel Substructure (base mat) in EEDB |
322.55 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Reinforc_steel_Substr |
0 |
131 |
Unit_EEDB_Labor_Reinforc_steel_Superstr |
Unit cost of Labor Reinforc steel Superstructure (shell) in EEDB |
326.13 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Reinforc_steel_Superstr |
0 |
132 |
Unit_EEDB_Labor_Reinforc_steel_Dome |
Unit cost of Labor Reinforc steel Superstructure (dome) in EEDB |
300.56 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Reinforc_steel_Dome |
0 |
133 |
Unit_EEDB_Labor_Reinforc_steel_Interior |
Unit cost of Labor Reinforc steel Interior structure in EEDB |
306.72 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Reinforc_steel_Interior |
0 |
134 |
Unit_EEDB_Labor_Rubbing_surfaces_Superstr |
Unit cost of Labor Rubbing surfaces Superstructure (shell) in EEDB |
8.32 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Rubbing_surfaces_Superstr |
0 |
135 |
Unit_EEDB_Labor_Rubbing_surfaces_Dome |
Unit cost of Labor Rubbing surfaces Superstructure (dome) in EEDB |
5.74 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Rubbing_surfaces_Dome |
0 |
136 |
Unit_EEDB_Labor_Rubbing_surfaces_Interior |
Unit cost of Labor Rubbing surfaces Interior structure in EEDB |
9.91 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Rubbing_surfaces_Interior |
0 |
137 |
Unit_EEDB_Labor_Waterproofing_Substr |
Unit cost of Labor Waterproofing Substructure (base mat) in EEDB |
4.58 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Waterproofing_Substr |
0 |
138 |
Unit_EEDB_Labor_Waterproofing_Superstr |
Unit cost of Labor Waterproofing Superstructure (shell) in EEDB |
0.84 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Waterproofing_Superstr |
0 |
139 |
Unit_EEDB_Labor_Waterproofing_Dome |
Unit cost of Labor Waterproofing Superstructure (dome) in EEDB |
0 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Waterproofing_Dome |
0 |
140 |
Unit_EEDB_Labor_Welded_wire_fabric_Substr |
Unit cost of Labor Welded wire fabric Substructure (base mat) in EEDB |
10.07 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_Welded_wire_fabric_Substr |
0 |
141 |
Unit_EEDB_Labor_Lighting_Power |
Unit cost of Labor Lighting Power in EEDB |
9.83 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Lighting_Power |
0 |
142 |
Unit_EEDB_Labor_Plumb_drains |
Unit cost of Labor Plumb drains in EEDB |
3.02 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Plumb_drains |
0 |
143 |
Unit_EEDB_Labor_Special_HVAC |
Unit cost of Labor Special HVAC in EEDB |
11.09 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Special_HVAC |
0 |
144 |
Unit_EEDB_Labor_other |
Unit cost of Labor other in EEDB |
0.53 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_other |
0 |
145 |
Unit_EEDB_Labor_Misc_steel_frames |
Unit cost of Labor miscellaneous steel frames in EEDB |
9.94 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Misc_steel_frames |
0 |
146 |
Unit_EEDB_Labor_React_cav_liner |
Unit cost of Labor Reactor cavity liner plate in EEDB |
745.94 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_React_cav_liner |
0 |
147 |
Unit_EEDB_Labor_Struct_steel |
Unit cost of Labor Struct steel in EEDB |
13.98 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_Struct_steel |
0 |
148 |
Unit_EEDB_Labor_cont_liner |
Unit cost of Labor Containment liner in EEDB |
780.33 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_cont_liner |
0 |
149 |
Unit_EEDB_Labor_fl_grate_handrail_stairs |
Unit cost of Labor Floor grating (galvanized), Handrail, Stair treads in EEDB |
1.75 |
dollar/m^3 |
NULL |
NULL |
Unit_Labor_fl_grate_handrail_stairs |
0 |
150 |
Unit_EEDB_Labor_painting |
Unit cost of Labor painting in EEDB |
86.8 |
dollar/m^2 |
NULL |
NULL |
Unit_Labor_painting |
0 |
151 |
Unit_EEDB_Mat_Cadweld_Substr |
Unit cost of Material Cadweld Substructure (base mat) in EEDB |
44.32 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Cadweld_Substr |
0 |
152 |
Unit_EEDB_Mat_Cadweld_Superstr |
Unit cost of Material Cadweld Superstructure (shell) in EEDB |
59.44 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Cadweld_Superstr |
0 |
153 |
Unit_EEDB_Mat_Cadweld_Dome |
Unit cost of Material Cadweld Superstructure (dome) in EEDB |
119.85 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Cadweld_Dome |
0 |
154 |
Unit_EEDB_Mat_Cadweld_Interior |
Unit cost of Material Cadweld Interior structure in EEDB |
25 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Cadweld_Interior |
0 |
155 |
Unit_EEDB_Mat_Concrete_Substr |
Unit cost of Material Concrete Substructure (base mat) in EEDB |
79.1 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Concrete_Substr |
0 |
156 |
Unit_EEDB_Mat_Concrete_Superstr |
Unit cost of Material Concrete Superstructure (shell) in EEDB |
54.47 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Concrete_Superstr |
0 |
157 |
Unit_EEDB_Mat_Concrete_Dome |
Unit cost of Material Concrete Superstructure (dome) in EEDB |
48.63 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Concrete_Dome |
0 |
158 |
Unit_EEDB_Mat_Concrete_Interior |
Unit cost of Material Concrete Interior structure in EEDB |
53.21 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Concrete_Interior |
0 |
159 |
Unit_EEDB_Mat_Constr_joints_Substr |
Unit cost of Material Construction joints Substructure (base mat) in EEDB |
8.9 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Constr_joints_Substr |
0 |
160 |
Unit_EEDB_Mat_Constr_joints_Superstr |
Unit cost of Material Construction joints Superstructure (shell) in EEDB |
7.63 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Constr_joints_Superstr |
0 |
161 |
Unit_EEDB_Mat_Constr_joints_Dome |
Unit cost of Material Construction joints Superstructure (dome) in EEDB |
2.91 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Constr_joints_Dome |
0 |
162 |
Unit_EEDB_Mat_Constr_joints_Interior |
Unit cost of Material Construction joints Interior structure in EEDB |
1.26 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Constr_joints_Interior |
0 |
163 |
Unit_EEDB_Mat_Embedded_steel_Substr |
Unit cost of Material Embedded steel Substructure (base mat) in EEDB |
1.88 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Embedded_steel_Substr |
0 |
164 |
Unit_EEDB_Mat_Embedded_steel_Superstr |
Unit cost of Material Embedded steel Superstructure (shell) in EEDB |
7.57 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Embedded_steel_Superstr |
0 |
165 |
Unit_EEDB_Mat_Embedded_steel_Dome |
Unit cost of Material Embedded steel Superstructure (dome) in EEDB |
0 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Embedded_steel_Dome |
0 |
166 |
Unit_EEDB_Mat_Embedded_steel_Interior |
Unit cost of Material Embedded steel Interior structure in EEDB |
159.73 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Embedded_steel_Interior |
0 |
167 |
Unit_EEDB_Mat_Formwork_Substr |
Unit cost of Material Formwork Substructure (base mat) in EEDB |
13.22 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Formwork_Substr |
0 |
168 |
Unit_EEDB_Mat_Formwork_Superstr |
Unit cost of Material Formwork Superstructure (shell) in EEDB |
13.65 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Formwork_Superstr |
0 |
169 |
Unit_EEDB_Mat_Formwork_Dome |
Unit cost of Material Formwork Superstructure (dome) in EEDB |
7.67 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Formwork_Dome |
0 |
170 |
Unit_EEDB_Mat_Formwork_Interior |
Unit cost of Material Formwork Interior structure in EEDB |
21.85 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Formwork_Interior |
0 |
171 |
Unit_EEDB_Mat_Maj_supp_embedments_Interior |
Unit cost of Material Major Support Embedments Interior structure in EEDB |
225.35 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Maj_supp_embedments_Interior |
0 |
172 |
Unit_EEDB_Mat_Reinforc_steel_Substr |
Unit cost of Material Reinforc steel Substructure (base mat) in EEDB |
364.73 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Reinforc_steel_Substr |
0 |
173 |
Unit_EEDB_Mat_Reinforc_steel_Superstr |
Unit cost of Material Reinforc steel Superstructure (shell) in EEDB |
258.95 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Reinforc_steel_Superstr |
0 |
174 |
Unit_EEDB_Mat_Reinforc_steel_Dome |
Unit cost of Material Reinforc steel Superstructure (dome) in EEDB |
238.65 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Reinforc_steel_Dome |
0 |
175 |
Unit_EEDB_Mat_Reinforc_steel_Interior |
Unit cost of Material Reinforc steel Interior structure in EEDB |
205.66 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Reinforc_steel_Interior |
0 |
176 |
Unit_EEDB_Mat_Rubbing_surfaces_Superstr |
Unit cost of Material Rubbing surfaces Superstructure (shell) in EEDB |
0.68 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Rubbing_surfaces_Superstr |
0 |
177 |
Unit_EEDB_Mat_Rubbing_surfaces_Dome |
Unit cost of Material Rubbing surfaces Superstructure (dome) in EEDB |
0.47 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Rubbing_surfaces_Dome |
0 |
178 |
Unit_EEDB_Mat_Rubbing_surfaces_Interior |
Unit cost of Material Rubbing surfaces Interior structure in EEDB |
0.82 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Rubbing_surfaces_Interior |
0 |
179 |
Unit_EEDB_Mat_Waterproofing_Substr |
Unit cost of Material Waterproofing Substructure (base mat) in EEDB |
2.43 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Waterproofing_Substr |
0 |
180 |
Unit_EEDB_Mat_Waterproofing_Superstr |
Unit cost of Material Waterproofing Superstructure (shell) in EEDB |
0.45 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Waterproofing_Superstr |
0 |
181 |
Unit_EEDB_Mat_Waterproofing_Dome |
Unit cost of Material Waterproofing Superstructure (dome) in EEDB |
0 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Waterproofing_Dome |
0 |
182 |
Unit_EEDB_Mat_Welded_wire_fabric_Substr |
Unit cost of Material Welded wire fabric Substructure (base mat) in EEDB |
5.19 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_Welded_wire_fabric_Substr |
0 |
183 |
Unit_EEDB_Mat_Lighting_Power |
Unit cost of Material Lighting Power in EEDB |
4.96 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Lighting_Power |
0 |
184 |
Unit_EEDB_Mat_Plumb_drains |
Unit cost of Material Plumb drains in EEDB |
1.54 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Plumb_drains |
0 |
185 |
Unit_EEDB_Mat_Special_HVAC |
Unit cost of Material Special HVAC in EEDB |
8.79 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Special_HVAC |
0 |
186 |
Unit_EEDB_Mat_other |
Unit cost of Material other in EEDB |
1.96 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_other |
0 |
187 |
Unit_EEDB_Mat_Misc_steel_frames |
Unit cost of Material miscellaneous steel frames in EEDB |
16.56 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Misc_steel_frames |
0 |
188 |
Unit_EEDB_Mat_React_cav_liner |
Unit cost of Material Reactor cavity liner plate in EEDB |
607.96 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_React_cav_liner |
0 |
189 |
Unit_EEDB_Mat_Struct_steel |
Unit cost of Material Struct steel in EEDB |
27.41 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_Struct_steel |
0 |
190 |
Unit_EEDB_Mat_cont_liner |
Unit cost of Material Containment liner in EEDB |
1203 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_cont_liner |
0 |
191 |
Unit_EEDB_Mat_fl_grate_handrail_stairs |
Unit cost of Material Floor grating (galvanized), Handrail, Stair treads in EEDB |
1.98 |
dollar/m^3 |
NULL |
NULL |
Unit_Mat_fl_grate_handrail_stairs |
0 |
192 |
Unit_EEDB_Mat_painting |
Unit cost of Material painting in EEDB |
24.68 |
dollar/m^2 |
NULL |
NULL |
Unit_Mat_painting |
0 |
193 |
Unit_Labor_Cadweld_Substr |
Unit cost of Labor Cadweld Substructure (base mat) in 2017 |
245.31 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Cadweld_Substr,infl |
Total_Labor_Cadweld_Substr |
0 |
194 |
Unit_Labor_Cadweld_Superstr |
Unit cost of Labor Cadweld Superstructure (shell) in 2017 |
329.02 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Cadweld_Superstr,infl |
Total_Labor_Cadweld_Superstr |
0 |
195 |
Unit_Labor_Cadweld_Dome |
Unit cost of Labor Cadweld Superstructure (dome) in 2017 |
663.34 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Cadweld_Dome,infl |
Total_Labor_Cadweld_Dome |
0 |
196 |
Unit_Labor_Cadweld_Interior |
Unit cost of Labor Cadweld Interior structure in 2017 |
138.36 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Cadweld_Interior,infl |
Total_Labor_Cadweld_Interior |
0 |
197 |
Unit_Labor_Concrete_Substr |
Unit cost of Labor Concrete Substructure (base mat) in 2017 |
208.17 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Concrete_Substr,infl |
Total_Labor_Concrete_Substr |
0 |
198 |
Unit_Labor_Concrete_Superstr |
Unit cost of Labor Concrete Superstructure (shell) in 2017 |
250.85 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Concrete_Superstr,infl |
Total_Labor_Concrete_Superstr |
0 |
199 |
Unit_Labor_Concrete_Dome |
Unit cost of Labor Concrete Superstructure (dome) in 2017 |
223.96 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Concrete_Dome,infl |
Total_Labor_Concrete_Dome |
0 |
200 |
Unit_Labor_Concrete_Interior |
Unit cost of Labor Concrete Interior structure in 2017 |
280.07 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Concrete_Interior,infl |
Total_Labor_Concrete_Interior |
0 |
201 |
Unit_Labor_Constr_joints_Substr |
Unit cost of Labor Construction joints Substructure (base mat) in 2017 |
41.65 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Constr_joints_Substr,infl |
Total_Labor_Constr_joints_Substr |
0 |
202 |
Unit_Labor_Constr_joints_Superstr |
Unit cost of Labor Construction joints Superstructure (shell) in 2017 |
35.71 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Constr_joints_Superstr,infl |
Total_Labor_Constr_joints_Superstr |
0 |
203 |
Unit_Labor_Constr_joints_Dome |
Unit cost of Labor Construction joints Superstructure (dome) in 2017 |
13.63 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Constr_joints_Dome,infl |
Total_Labor_Constr_joints_Dome |
0 |
204 |
Unit_Labor_Constr_joints_Interior |
Unit cost of Labor Construction joints Interior structure in 2017 |
5.88 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Constr_joints_Interior,infl |
Total_Labor_Constr_joints_Interior |
0 |
205 |
Unit_Labor_Embedded_steel_Substr |
Unit cost of Labor Embedded steel Substructure (base mat) in 2017 |
11.42 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Embedded_steel_Substr,infl |
Total_Labor_Embedded_steel_Substr |
0 |
206 |
Unit_Labor_Embedded_steel_Superstr |
Unit cost of Labor Embedded steel Superstructure (shell) in 2017 |
45.87 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Embedded_steel_Superstr,infl |
Total_Labor_Embedded_steel_Superstr |
0 |
207 |
Unit_Labor_Embedded_steel_Dome |
Unit cost of Labor Embedded steel Superstructure (dome) in 2017 |
0 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Embedded_steel_Dome,infl |
Total_Labor_Embedded_steel_Dome |
0 |
208 |
Unit_Labor_Embedded_steel_Interior |
Unit cost of Labor Embedded steel Interior structure in 2017 |
967.76 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Embedded_steel_Interior,infl |
Total_Labor_Embedded_steel_Interior |
0 |
209 |
Unit_Labor_Formwork_Substr |
Unit cost of Labor Formwork Substructure (base mat) in 2017 |
267.27 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Formwork_Substr,infl |
Total_Labor_Formwork_Substr |
0 |
210 |
Unit_Labor_Formwork_Superstr |
Unit cost of Labor Formwork Superstructure (shell) in 2017 |
315.27 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Formwork_Superstr,infl |
Total_Labor_Formwork_Superstr |
0 |
211 |
Unit_Labor_Formwork_Dome |
Unit cost of Labor Formwork Superstructure (dome) in 2017 |
168.38 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Formwork_Dome,infl |
Total_Labor_Formwork_Dome |
0 |
212 |
Unit_Labor_Formwork_Interior |
Unit cost of Labor Formwork Interior structure in 2017 |
664.58 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Formwork_Interior,infl |
Total_Labor_Formwork_Interior |
0 |
213 |
Unit_Labor_Maj_supp_embedments_Interior |
Unit cost of Labor Major Support Embedments Interior structure in 2017 |
440.71 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Maj_supp_embedments_Interior,infl |
Total_Labor_Maj_supp_embedments_Interior |
0 |
214 |
Unit_Labor_Reinforc_steel_Substr |
Unit cost of Labor Reinforc steel Substructure (base mat) in 2017 |
925.88 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Reinforc_steel_Substr,infl |
Total_Labor_Reinforc_steel_Substr |
0 |
215 |
Unit_Labor_Reinforc_steel_Superstr |
Unit cost of Labor Reinforc steel Superstructure (shell) in 2017 |
936.16 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Reinforc_steel_Superstr,infl |
Total_Labor_Reinforc_steel_Superstr |
0 |
216 |
Unit_Labor_Reinforc_steel_Dome |
Unit cost of Labor Reinforc steel Superstructure (dome) in 2017 |
862.76 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Reinforc_steel_Dome,infl |
Total_Labor_Reinforc_steel_Dome |
0 |
217 |
Unit_Labor_Reinforc_steel_Interior |
Unit cost of Labor Reinforc steel Interior structure in 2017 |
880.44 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Reinforc_steel_Interior,infl |
Total_Labor_Reinforc_steel_Interior |
0 |
218 |
Unit_Labor_Rubbing_surfaces_Superstr |
Unit cost of Labor Rubbing surfaces Superstructure (shell) in 2017 |
23.88 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Rubbing_surfaces_Superstr,infl |
Total_Labor_Rubbing_surfaces_Superstr |
0 |
219 |
Unit_Labor_Rubbing_surfaces_Dome |
Unit cost of Labor Rubbing surfaces Superstructure (dome) in 2017 |
16.48 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Rubbing_surfaces_Dome,infl |
Total_Labor_Rubbing_surfaces_Dome |
0 |
220 |
Unit_Labor_Rubbing_surfaces_Interior |
Unit cost of Labor Rubbing surfaces Interior structure in 2017 |
28.45 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Rubbing_surfaces_Interior,infl |
Total_Labor_Rubbing_surfaces_Interior |
0 |
221 |
Unit_Labor_Waterproofing_Substr |
Unit cost of Labor Waterproofing Substructure (base mat) in 2017 |
13.15 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Waterproofing_Substr,infl |
Total_Labor_Waterproofing_Substr |
0 |
222 |
Unit_Labor_Waterproofing_Superstr |
Unit cost of Labor Waterproofing Superstructure (shell) in 2017 |
2.41 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Waterproofing_Superstr,infl |
Total_Labor_Waterproofing_Superstr |
0 |
223 |
Unit_Labor_Waterproofing_Dome |
Unit cost of Labor Waterproofing Superstructure (dome) in 2017 |
0 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Waterproofing_Dome,infl |
Total_Labor_Waterproofing_Dome |
0 |
224 |
Unit_Labor_Welded_wire_fabric_Substr |
Unit cost of Labor Welded wire fabric Substructure (base mat) in 2017 |
28.91 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_Welded_wire_fabric_Substr,infl |
Total_Labor_Welded_wire_fabric_Substr |
0 |
225 |
Unit_Labor_Lighting_Power |
Unit cost of Labor Lighting Power in 2017 |
28.22 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Lighting_Power,infl |
Total_Labor_Lighting_Power |
0 |
226 |
Unit_Labor_Plumb_drains |
Unit cost of Labor Plumb drains in 2017 |
8.67 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Plumb_drains,infl |
Total_Labor_Plumb_drains |
0 |
227 |
Unit_Labor_Special_HVAC |
Unit cost of Labor Special HVAC in 2017 |
31.83 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Special_HVAC,infl |
Total_Labor_Special_HVAC |
0 |
228 |
Unit_Labor_other |
Unit cost of Labor other in 2017 |
1.52 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_other,infl |
Total_Labor_other |
0 |
229 |
Unit_Labor_Misc_steel_frames |
Unit cost of Labor miscellaneous steel frames in 2017 |
28.53 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Misc_steel_frames,infl |
Total_Labor_Misc_steel_frames |
0 |
230 |
Unit_Labor_React_cav_liner |
Unit cost of Labor Reactor cavity liner plate in 2017 |
2141.22 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_React_cav_liner,infl |
Total_Labor_React_cav_liner |
0 |
231 |
Unit_Labor_Struct_steel |
Unit cost of Labor Struct steel in 2017 |
40.13 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_Struct_steel,infl |
Total_Labor_Struct_steel |
0 |
232 |
Unit_Labor_cont_liner |
Unit cost of Labor Containment liner in 2017 |
2239.94 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_cont_liner,infl |
Total_Labor_cont_liner |
0 |
233 |
Unit_Labor_fl_grate_handrail_stairs |
Unit cost of Labor Floor grating (galvanized), Handrail, Stair treads in 2017 |
5.02 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Labor_fl_grate_handrail_stairs,infl |
Total_Labor_fl_grate_handrail_stairs |
0 |
234 |
Unit_Labor_painting |
Unit cost of Labor painting in 2017 |
249.16 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Labor_painting,infl |
Total_Labor_painting |
0 |
235 |
Unit_Mat_Cadweld_Substr |
Unit cost of Material Cadweld Substructure (base mat) in 2017 |
127.22 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Cadweld_Substr,infl |
Total_Mat_Cadweld_Substr |
0 |
236 |
Unit_Mat_Cadweld_Superstr |
Unit cost of Material Cadweld Superstructure (shell) in 2017 |
170.62 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Cadweld_Superstr,infl |
Total_Mat_Cadweld_Superstr |
0 |
237 |
Unit_Mat_Cadweld_Dome |
Unit cost of Material Cadweld Superstructure (dome) in 2017 |
344.03 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Cadweld_Dome,infl |
Total_Mat_Cadweld_Dome |
0 |
238 |
Unit_Mat_Cadweld_Interior |
Unit cost of Material Cadweld Interior structure in 2017 |
71.76 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Cadweld_Interior,infl |
Total_Mat_Cadweld_Interior |
0 |
239 |
Unit_Mat_Concrete_Substr |
Unit cost of Material Concrete Substructure (base mat) in 2017 |
227.06 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Concrete_Substr,infl |
Total_Mat_Concrete_Substr |
0 |
240 |
Unit_Mat_Concrete_Superstr |
Unit cost of Material Concrete Superstructure (shell) in 2017 |
156.36 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Concrete_Superstr,infl |
Total_Mat_Concrete_Superstr |
0 |
241 |
Unit_Mat_Concrete_Dome |
Unit cost of Material Concrete Superstructure (dome) in 2017 |
139.59 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Concrete_Dome,infl |
Total_Mat_Concrete_Dome |
0 |
242 |
Unit_Mat_Concrete_Interior |
Unit cost of Material Concrete Interior structure in 2017 |
152.74 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Concrete_Interior,infl |
Total_Mat_Concrete_Interior |
0 |
243 |
Unit_Mat_Constr_joints_Substr |
Unit cost of Material Construction joints Substructure (base mat) in 2017 |
25.55 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Constr_joints_Substr,infl |
Total_Mat_Constr_joints_Substr |
0 |
244 |
Unit_Mat_Constr_joints_Superstr |
Unit cost of Material Construction joints Superstructure (shell) in 2017 |
21.9 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Constr_joints_Superstr,infl |
Total_Mat_Constr_joints_Superstr |
0 |
245 |
Unit_Mat_Constr_joints_Dome |
Unit cost of Material Construction joints Superstructure (dome) in 2017 |
8.35 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Constr_joints_Dome,infl |
Total_Mat_Constr_joints_Dome |
0 |
246 |
Unit_Mat_Constr_joints_Interior |
Unit cost of Material Construction joints Interior structure in 2017 |
3.62 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Constr_joints_Interior,infl |
Total_Mat_Constr_joints_Interior |
0 |
247 |
Unit_Mat_Embedded_steel_Substr |
Unit cost of Material Embedded steel Substructure (base mat) in 2017 |
5.4 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Embedded_steel_Substr,infl |
Total_Mat_Embedded_steel_Substr |
0 |
248 |
Unit_Mat_Embedded_steel_Superstr |
Unit cost of Material Embedded steel Superstructure (shell) in 2017 |
21.73 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Embedded_steel_Superstr,infl |
Total_Mat_Embedded_steel_Superstr |
0 |
249 |
Unit_Mat_Embedded_steel_Dome |
Unit cost of Material Embedded steel Superstructure (dome) in 2017 |
0 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Embedded_steel_Dome,infl |
Total_Mat_Embedded_steel_Dome |
0 |
250 |
Unit_Mat_Embedded_steel_Interior |
Unit cost of Material Embedded steel Interior structure in 2017 |
458.51 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Embedded_steel_Interior,infl |
Total_Mat_Embedded_steel_Interior |
0 |
251 |
Unit_Mat_Formwork_Substr |
Unit cost of Material Formwork Substructure (base mat) in 2017 |
37.95 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Formwork_Substr,infl |
Total_Mat_Formwork_Substr |
0 |
252 |
Unit_Mat_Formwork_Superstr |
Unit cost of Material Formwork Superstructure (shell) in 2017 |
39.18 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Formwork_Superstr,infl |
Total_Mat_Formwork_Superstr |
0 |
253 |
Unit_Mat_Formwork_Dome |
Unit cost of Material Formwork Superstructure (dome) in 2017 |
22.02 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Formwork_Dome,infl |
Total_Mat_Formwork_Dome |
0 |
254 |
Unit_Mat_Formwork_Interior |
Unit cost of Material Formwork Interior structure in 2017 |
62.72 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Formwork_Interior,infl |
Total_Mat_Formwork_Interior |
0 |
255 |
Unit_Mat_Maj_supp_embedments_Interior |
Unit cost of Material Major Support Embedments Interior structure in 2017 |
646.87 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Maj_supp_embedments_Interior,infl |
Total_Mat_Maj_supp_embedments_Interior |
0 |
256 |
Unit_Mat_Reinforc_steel_Substr |
Unit cost of Material Reinforc steel Substructure (base mat) in 2017 |
1046.96 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Reinforc_steel_Substr,infl |
Total_Mat_Reinforc_steel_Substr |
0 |
257 |
Unit_Mat_Reinforc_steel_Superstr |
Unit cost of Material Reinforc steel Superstructure (shell) in 2017 |
743.32 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Reinforc_steel_Superstr,infl |
Total_Mat_Reinforc_steel_Superstr |
0 |
258 |
Unit_Mat_Reinforc_steel_Dome |
Unit cost of Material Reinforc steel Superstructure (dome) in 2017 |
685.05 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Reinforc_steel_Dome,infl |
Total_Mat_Reinforc_steel_Dome |
0 |
259 |
Unit_Mat_Reinforc_steel_Interior |
Unit cost of Material Reinforc steel Interior structure in 2017 |
590.35 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Reinforc_steel_Interior,infl |
Total_Mat_Reinforc_steel_Interior |
0 |
260 |
Unit_Mat_Rubbing_surfaces_Superstr |
Unit cost of Material Rubbing surfaces Superstructure (shell) in 2017 |
1.95 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Rubbing_surfaces_Superstr,infl |
Total_Mat_Rubbing_surfaces_Superstr |
0 |
261 |
Unit_Mat_Rubbing_surfaces_Dome |
Unit cost of Material Rubbing surfaces Superstructure (dome) in 2017 |
1.35 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Rubbing_surfaces_Dome,infl |
Total_Mat_Rubbing_surfaces_Dome |
0 |
262 |
Unit_Mat_Rubbing_surfaces_Interior |
Unit cost of Material Rubbing surfaces Interior structure in 2017 |
2.35 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Rubbing_surfaces_Interior,infl |
Total_Mat_Rubbing_surfaces_Interior |
0 |
263 |
Unit_Mat_Waterproofing_Substr |
Unit cost of Material Waterproofing Substructure (base mat) in 2017 |
6.98 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Waterproofing_Substr,infl |
Total_Mat_Waterproofing_Substr |
0 |
264 |
Unit_Mat_Waterproofing_Superstr |
Unit cost of Material Waterproofing Superstructure (shell) in 2017 |
1.29 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Waterproofing_Superstr,infl |
Total_Mat_Waterproofing_Superstr |
0 |
265 |
Unit_Mat_Waterproofing_Dome |
Unit cost of Material Waterproofing Superstructure (dome) in 2017 |
0 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Waterproofing_Dome,infl |
Total_Mat_Waterproofing_Dome |
0 |
266 |
Unit_Mat_Welded_wire_fabric_Substr |
Unit cost of Material Welded wire fabric Substructure (base mat) in 2017 |
14.9 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_Welded_wire_fabric_Substr,infl |
Total_Mat_Welded_wire_fabric_Substr |
0 |
267 |
Unit_Mat_Lighting_Power |
Unit cost of Material Lighting Power in 2017 |
14.24 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Lighting_Power,infl |
Total_Mat_Lighting_Power |
0 |
268 |
Unit_Mat_Plumb_drains |
Unit cost of Material Plumb drains in 2017 |
4.42 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Plumb_drains,infl |
Total_Mat_Plumb_drains |
0 |
269 |
Unit_Mat_Special_HVAC |
Unit cost of Material Special HVAC in 2017 |
25.23 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Special_HVAC,infl |
Total_Mat_Special_HVAC |
0 |
270 |
Unit_Mat_other |
Unit cost of Material other in 2017 |
5.63 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_other,infl |
Total_Mat_other |
0 |
271 |
Unit_Mat_Misc_steel_frames |
Unit cost of Material miscellaneous steel frames in 2017 |
47.54 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Misc_steel_frames,infl |
Total_Mat_Misc_steel_frames |
0 |
272 |
Unit_Mat_React_cav_liner |
Unit cost of Material Reactor cavity liner plate in 2017 |
1745.15 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_React_cav_liner,infl |
Total_Mat_React_cav_liner |
0 |
273 |
Unit_Mat_Struct_steel |
Unit cost of Material Struct steel in 2017 |
78.68 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_Struct_steel,infl |
Total_Mat_Struct_steel |
0 |
274 |
Unit_Mat_cont_liner |
Unit cost of Material Containment liner in 2017 |
3453.21 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_cont_liner,infl |
Total_Mat_cont_liner |
0 |
275 |
Unit_Mat_fl_grate_handrail_stairs |
Unit cost of Material Floor grating (galvanized), Handrail, Stair treads in 2017 |
5.68 |
dollar/m^3 |
unitcost_v_eedb_to_accert |
Unit_EEDB_Mat_fl_grate_handrail_stairs,infl |
Total_Mat_fl_grate_handrail_stairs |
0 |
276 |
Unit_Mat_painting |
Unit cost of Material painting in 2017 |
70.84 |
dollar/m^2 |
unitcost_s_eedb_to_accert |
Unit_EEDB_Mat_painting,infl |
Total_Mat_painting |
0 |
277 |
Total_Labor_Cadweld_Substr |
Total cost of Labor Cadweld Substructure (base mat) in 2017 |
545576.13 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Cadweld_Substr,Basemat_v_m3 |
Sum_Labor_Cadweld |
0 |
278 |
Total_Labor_Cadweld_Superstr |
Total cost of Labor Cadweld Superstructure (shell) in 2017 |
1459105.66 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Cadweld_Superstr,Walls_v_m3 |
Sum_Labor_Cadweld |
0 |
279 |
Total_Labor_Cadweld_Dome |
Total cost of Labor Cadweld Superstructure (dome) in 2017 |
962092.18 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Cadweld_Dome,Dome_v_m3 |
Sum_Labor_Cadweld |
0 |
280 |
Total_Labor_Cadweld_Interior |
Total cost of Labor Cadweld Interior structure in 2017 |
313811.43 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Cadweld_Interior,Internal_v_m3 |
Sum_Labor_Cadweld |
0 |
281 |
Total_Labor_Concrete_Substr |
Total cost of Labor Concrete Substructure (base mat) in 2017 |
462967.25 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Concrete_Substr,Basemat_v_m3 |
Sum_Labor_Concrete |
0 |
282 |
Total_Labor_Concrete_Superstr |
Total cost of Labor Concrete Superstructure (shell) in 2017 |
1112469.41 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Concrete_Superstr,Walls_v_m3 |
Sum_Labor_Concrete |
0 |
283 |
Total_Labor_Concrete_Dome |
Total cost of Labor Concrete Superstructure (dome) in 2017 |
324819.04 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Concrete_Dome,Dome_v_m3 |
Sum_Labor_Concrete |
0 |
284 |
Total_Labor_Concrete_Interior |
Total cost of Labor Concrete Interior structure in 2017 |
635240.28 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Concrete_Interior,Internal_v_m3 |
Sum_Labor_Concrete |
0 |
285 |
Total_Labor_Constr_joints_Substr |
Total cost of Labor Construction joints Substructure (base mat) in 2017 |
30391 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Constr_joints_Substr,Basemat_s_m2 |
Sum_Labor_Constr_joints |
0 |
286 |
Total_Labor_Constr_joints_Superstr |
Total cost of Labor Construction joints Superstructure (shell) in 2017 |
230913.45 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Constr_joints_Superstr,Walls_s_m2 |
Sum_Labor_Constr_joints |
0 |
287 |
Total_Labor_Constr_joints_Dome |
Total cost of Labor Construction joints Superstructure (dome) in 2017 |
37107.07 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Constr_joints_Dome,Dome_s_m2 |
Sum_Labor_Constr_joints |
0 |
288 |
Total_Labor_Constr_joints_Interior |
Total cost of Labor Construction joints Interior structure in 2017 |
21894.28 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Constr_joints_Interior,Internal_s_m2 |
Sum_Labor_Constr_joints |
0 |
289 |
Total_Labor_Embedded_steel_Substr |
Total cost of Labor Embedded steel Substructure (base mat) in 2017 |
25408.3 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Embedded_steel_Substr,Basemat_v_m3 |
Sum_Labor_Embedded_steel |
0 |
290 |
Total_Labor_Embedded_steel_Superstr |
Total cost of Labor Embedded steel Superstructure (shell) in 2017 |
203424.43 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Embedded_steel_Superstr,Walls_v_m3 |
Sum_Labor_Embedded_steel |
0 |
291 |
Total_Labor_Embedded_steel_Dome |
Total cost of Labor Embedded steel Superstructure (dome) in 2017 |
0 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Embedded_steel_Dome,Dome_v_m3 |
Sum_Labor_Embedded_steel |
0 |
292 |
Total_Labor_Embedded_steel_Interior |
Total cost of Labor Embedded steel Interior structure in 2017 |
2194987.28 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Embedded_steel_Interior,Internal_v_m3 |
Sum_Labor_Embedded_steel |
0 |
293 |
Total_Labor_Formwork_Substr |
Total cost of Labor Formwork Substructure (base mat) in 2017 |
195017.61 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Formwork_Substr,Basemat_s_m2 |
Sum_Labor_Formwork |
0 |
294 |
Total_Labor_Formwork_Superstr |
Total cost of Labor Formwork Superstructure (shell) in 2017 |
2038683.66 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Formwork_Superstr,Walls_s_m2 |
Sum_Labor_Formwork |
0 |
295 |
Total_Labor_Formwork_Dome |
Total cost of Labor Formwork Superstructure (dome) in 2017 |
458252.79 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Formwork_Dome,Dome_s_m2 |
Sum_Labor_Formwork |
0 |
296 |
Total_Labor_Formwork_Interior |
Total cost of Labor Formwork Interior structure in 2017 |
2472664.99 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Formwork_Interior,Internal_s_m2 |
Sum_Labor_Formwork |
0 |
297 |
Total_Labor_Maj_supp_embedments_Interior |
Total cost of Labor Major Support Embedments Interior structure in 2017 |
999574.05 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Maj_supp_embedments_Interior,Internal_v_m3 |
Sum_Labor_Maj_supp_embedments |
0 |
298 |
Total_Labor_Reinforc_steel_Substr |
Total cost of Labor Reinforc steel Substructure (base mat) in 2017 |
2059157.28 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Reinforc_steel_Substr,Basemat_v_m3 |
Sum_Labor_Reinforc_steel |
0 |
299 |
Total_Labor_Reinforc_steel_Superstr |
Total cost of Labor Reinforc steel Superstructure (shell) in 2017 |
4151615.16 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Reinforc_steel_Superstr,Walls_v_m3 |
Sum_Labor_Reinforc_steel |
0 |
300 |
Total_Labor_Reinforc_steel_Dome |
Total cost of Labor Reinforc steel Superstructure (dome) in 2017 |
1251315.18 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Reinforc_steel_Dome,Dome_v_m3 |
Sum_Labor_Reinforc_steel |
0 |
301 |
Total_Labor_Reinforc_steel_Interior |
Total cost of Labor Reinforc steel Interior structure in 2017 |
1996934.5 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Reinforc_steel_Interior,Internal_v_m3 |
Sum_Labor_Reinforc_steel |
0 |
302 |
Total_Labor_Rubbing_surfaces_Superstr |
Total cost of Labor Rubbing surfaces Superstructure (shell) in 2017 |
154437.29 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Rubbing_surfaces_Superstr,Walls_s_m2 |
Sum_Labor_Rubbing_surfaces |
0 |
303 |
Total_Labor_Rubbing_surfaces_Dome |
Total cost of Labor Rubbing surfaces Superstructure (dome) in 2017 |
44840.96 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Rubbing_surfaces_Dome,Dome_s_m2 |
Sum_Labor_Rubbing_surfaces |
0 |
304 |
Total_Labor_Rubbing_surfaces_Interior |
Total cost of Labor Rubbing surfaces Interior structure in 2017 |
105840.14 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Rubbing_surfaces_Interior,Internal_s_m2 |
Sum_Labor_Rubbing_surfaces |
0 |
305 |
Total_Labor_Waterproofing_Substr |
Total cost of Labor Waterproofing Substructure (base mat) in 2017 |
9592.75 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Waterproofing_Substr,Basemat_s_m2 |
Sum_Labor_Waterproofing |
0 |
306 |
Total_Labor_Waterproofing_Superstr |
Total cost of Labor Waterproofing Superstructure (shell) in 2017 |
15592.23 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Waterproofing_Superstr,Walls_s_m2 |
Sum_Labor_Waterproofing |
0 |
307 |
Total_Labor_Waterproofing_Dome |
Total cost of Labor Waterproofing Superstructure (dome) in 2017 |
0 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Waterproofing_Dome,Dome_s_m2 |
Sum_Labor_Waterproofing |
0 |
308 |
Total_Labor_Welded_wire_fabric_Substr |
Total cost of Labor Welded wire fabric Substructure (base mat) in 2017 |
21091.48 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Welded_wire_fabric_Substr,Basemat_s_m2 |
Sum_Labor_Welded_wire_fabric |
0 |
309 |
Total_Labor_Lighting_Power |
Total cost of Labor Lighting Power in 2017 |
771075.94 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Lighting_Power,Intern_tot_v_m3 |
Tot_Labor_equipment |
0 |
310 |
Total_Labor_Plumb_drains |
Total cost of Labor Plumb drains in 2017 |
236892.1 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Plumb_drains,Intern_tot_v_m3 |
Tot_Labor_equipment |
0 |
311 |
Total_Labor_Special_HVAC |
Total cost of Labor Special HVAC in 2017 |
869911.71 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Special_HVAC,Intern_tot_v_m3 |
Tot_Labor_equipment |
0 |
312 |
Total_Labor_other |
Total cost of Labor other in 2017 |
41573.78 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_other,Intern_tot_v_m3 |
Tot_Labor_equipment |
0 |
313 |
Total_Labor_Misc_steel_frames |
Total cost of Labor miscellaneous steel frames in 2017 |
296090.96 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Misc_steel_frames,Struct_v_m3 |
Tot_Labor_others |
0 |
314 |
Total_Labor_React_cav_liner |
Total cost of Labor Reactor cavity liner plate in 2017 |
2188185.87 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_React_cav_liner,React_cav_A_m2 |
Tot_Labor_others |
0 |
315 |
Total_Labor_Struct_steel |
Total cost of Labor Struct steel in 2017 |
416433.77 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_Struct_steel,Struct_v_m3 |
Tot_Labor_others |
0 |
316 |
Total_Labor_cont_liner |
Total cost of Labor Containment liner in 2017 |
11081657.51 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_cont_liner,Liner_s_m2 |
Tot_Labor_others |
0 |
317 |
Total_Labor_fl_grate_handrail_stairs |
Total cost of Labor Floor grating (galvanized), Handrail, Stair treads in 2017 |
137271.91 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_fl_grate_handrail_stairs,Intern_tot_v_m3 |
Tot_Labor_others |
0 |
318 |
Total_Labor_painting |
Total cost of Labor painting in 2017 |
3366865.17 |
dollar |
tol_contaiment_ce_cost |
Unit_Labor_painting,Surf_paint_m2 |
Tot_Labor_others |
0 |
319 |
Total_Mat_Cadweld_Substr |
Total cost of Material Cadweld Substructure (base mat) in 2017 |
282938.62 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Cadweld_Substr,Basemat_v_m3 |
Sum_Mat_Cadweld |
0 |
320 |
Total_Mat_Cadweld_Superstr |
Total cost of Material Cadweld Superstructure (shell) in 2017 |
756667.6 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Cadweld_Superstr,Walls_v_m3 |
Sum_Mat_Cadweld |
0 |
321 |
Total_Mat_Cadweld_Dome |
Total cost of Material Cadweld Superstructure (dome) in 2017 |
498969.01 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Cadweld_Dome,Dome_v_m3 |
Sum_Mat_Cadweld |
0 |
322 |
Total_Mat_Cadweld_Interior |
Total cost of Material Cadweld Interior structure in 2017 |
162765.27 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Cadweld_Interior,Internal_v_m3 |
Sum_Mat_Cadweld |
0 |
323 |
Total_Mat_Concrete_Substr |
Total cost of Material Concrete Substructure (base mat) in 2017 |
504973.93 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Concrete_Substr,Basemat_v_m3 |
Sum_Mat_Concrete |
0 |
324 |
Total_Mat_Concrete_Superstr |
Total cost of Material Concrete Superstructure (shell) in 2017 |
693399.8 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Concrete_Superstr,Walls_v_m3 |
Sum_Mat_Concrete |
0 |
325 |
Total_Mat_Concrete_Dome |
Total cost of Material Concrete Superstructure (dome) in 2017 |
202460.27 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Concrete_Dome,Dome_v_m3 |
Sum_Mat_Concrete |
0 |
326 |
Total_Mat_Concrete_Interior |
Total cost of Material Concrete Interior structure in 2017 |
346429.59 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Concrete_Interior,Internal_v_m3 |
Sum_Mat_Concrete |
0 |
327 |
Total_Mat_Constr_joints_Substr |
Total cost of Material Construction joints Substructure (base mat) in 2017 |
18640.93 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Constr_joints_Substr,Basemat_s_m2 |
Sum_Mat_Constr_joints |
0 |
328 |
Total_Mat_Constr_joints_Superstr |
Total cost of Material Construction joints Superstructure (shell) in 2017 |
141629.39 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Constr_joints_Superstr,Walls_s_m2 |
Sum_Mat_Constr_joints |
0 |
329 |
Total_Mat_Constr_joints_Dome |
Total cost of Material Construction joints Superstructure (dome) in 2017 |
22732.96 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Constr_joints_Dome,Dome_s_m2 |
Sum_Mat_Constr_joints |
0 |
330 |
Total_Mat_Constr_joints_Interior |
Total cost of Material Construction joints Interior structure in 2017 |
13456.97 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Constr_joints_Interior,Internal_s_m2 |
Sum_Mat_Constr_joints |
0 |
331 |
Total_Mat_Embedded_steel_Substr |
Total cost of Material Embedded steel Substructure (base mat) in 2017 |
12001.91 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Embedded_steel_Substr,Basemat_v_m3 |
Sum_Mat_Embedded_steel |
0 |
332 |
Total_Mat_Embedded_steel_Superstr |
Total cost of Material Embedded steel Superstructure (shell) in 2017 |
96365.64 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Embedded_steel_Superstr,Walls_v_m3 |
Sum_Mat_Embedded_steel |
0 |
333 |
Total_Mat_Embedded_steel_Dome |
Total cost of Material Embedded steel Superstructure (dome) in 2017 |
0 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Embedded_steel_Dome,Dome_v_m3 |
Sum_Mat_Embedded_steel |
0 |
334 |
Total_Mat_Embedded_steel_Interior |
Total cost of Material Embedded steel Interior structure in 2017 |
1039939.84 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Embedded_steel_Interior,Internal_v_m3 |
Sum_Mat_Embedded_steel |
0 |
335 |
Total_Mat_Formwork_Substr |
Total cost of Material Formwork Substructure (base mat) in 2017 |
27689.11 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Formwork_Substr,Basemat_s_m2 |
Sum_Mat_Formwork |
0 |
336 |
Total_Mat_Formwork_Superstr |
Total cost of Material Formwork Superstructure (shell) in 2017 |
253373.69 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Formwork_Superstr,Walls_s_m2 |
Sum_Mat_Formwork |
0 |
337 |
Total_Mat_Formwork_Dome |
Total cost of Material Formwork Superstructure (dome) in 2017 |
59918.15 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Formwork_Dome,Dome_s_m2 |
Sum_Mat_Formwork |
0 |
338 |
Total_Mat_Formwork_Interior |
Total cost of Material Formwork Interior structure in 2017 |
233360.96 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Formwork_Interior,Internal_s_m2 |
Sum_Mat_Formwork |
0 |
339 |
Total_Mat_Maj_supp_embedments_Interior |
Total cost of Material Major Support Embedments Interior structure in 2017 |
1467166.11 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Maj_supp_embedments_Interior,Internal_v_m3 |
Sum_Mat_Maj_supp_embedments |
0 |
340 |
Total_Mat_Reinforc_steel_Substr |
Total cost of Material Reinforc steel Substructure (base mat) in 2017 |
2328434.14 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Reinforc_steel_Substr,Basemat_v_m3 |
Sum_Mat_Reinforc_steel |
0 |
341 |
Total_Mat_Reinforc_steel_Superstr |
Total cost of Material Reinforc steel Superstructure (shell) in 2017 |
3296417.82 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Reinforc_steel_Superstr,Walls_v_m3 |
Sum_Mat_Reinforc_steel |
0 |
342 |
Total_Mat_Reinforc_steel_Dome |
Total cost of Material Reinforc steel Superstructure (dome) in 2017 |
993566.57 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Reinforc_steel_Dome,Dome_v_m3 |
Sum_Mat_Reinforc_steel |
0 |
343 |
Total_Mat_Reinforc_steel_Interior |
Total cost of Material Reinforc steel Interior structure in 2017 |
1338972.19 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Reinforc_steel_Interior,Internal_v_m3 |
Sum_Mat_Reinforc_steel |
0 |
344 |
Total_Mat_Rubbing_surfaces_Superstr |
Total cost of Material Rubbing surfaces Superstructure (shell) in 2017 |
12622.28 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Rubbing_surfaces_Superstr,Walls_s_m2 |
Sum_Mat_Rubbing_surfaces |
0 |
345 |
Total_Mat_Rubbing_surfaces_Dome |
Total cost of Material Rubbing surfaces Superstructure (dome) in 2017 |
3671.65 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Rubbing_surfaces_Dome,Dome_s_m2 |
Sum_Mat_Rubbing_surfaces |
0 |
346 |
Total_Mat_Rubbing_surfaces_Interior |
Total cost of Material Rubbing surfaces Interior structure in 2017 |
8757.71 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Rubbing_surfaces_Interior,Internal_s_m2 |
Sum_Mat_Rubbing_surfaces |
0 |
347 |
Total_Mat_Waterproofing_Substr |
Total cost of Material Waterproofing Substructure (base mat) in 2017 |
5089.6 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Waterproofing_Substr,Basemat_s_m2 |
Sum_Mat_Waterproofing |
0 |
348 |
Total_Mat_Waterproofing_Superstr |
Total cost of Material Waterproofing Superstructure (shell) in 2017 |
8352.98 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Waterproofing_Superstr,Walls_s_m2 |
Sum_Mat_Waterproofing |
0 |
349 |
Total_Mat_Waterproofing_Dome |
Total cost of Material Waterproofing Superstructure (dome) in 2017 |
0 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Waterproofing_Dome,Dome_s_m2 |
Sum_Mat_Waterproofing |
0 |
350 |
Total_Mat_Welded_wire_fabric_Substr |
Total cost of Material Welded wire fabric Substructure (base mat) in 2017 |
10870.38 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Welded_wire_fabric_Substr,Basemat_s_m2 |
Sum_Mat_Welded_wire_fabric |
0 |
351 |
Total_Mat_Lighting_Power |
Total cost of Material Lighting Power in 2017 |
389067.82 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Lighting_Power,Intern_tot_v_m3 |
Tot_Mat_equipment |
0 |
352 |
Total_Mat_Plumb_drains |
Total cost of Material Plumb drains in 2017 |
120799.28 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Plumb_drains,Intern_tot_v_m3 |
Tot_Mat_equipment |
0 |
353 |
Total_Mat_Special_HVAC |
Total cost of Material Special HVAC in 2017 |
689497.2 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Special_HVAC,Intern_tot_v_m3 |
Tot_Mat_equipment |
0 |
354 |
Total_Mat_other |
Total cost of Material other in 2017 |
153744.54 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_other,Intern_tot_v_m3 |
Tot_Mat_equipment |
0 |
355 |
Total_Mat_Misc_steel_frames |
Total cost of Material miscellaneous steel frames in 2017 |
493286.35 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Misc_steel_frames,Struct_v_m3 |
Tot_Mat_others |
0 |
356 |
Total_Mat_React_cav_liner |
Total cost of Material Reactor cavity liner plate in 2017 |
1783426.93 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_React_cav_liner,React_cav_A_m2 |
Tot_Mat_others |
0 |
357 |
Total_Mat_Struct_steel |
Total cost of Material Struct steel in 2017 |
816484.24 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_Struct_steel,Struct_v_m3 |
Tot_Mat_others |
0 |
358 |
Total_Mat_cont_liner |
Total cost of Material Containment liner in 2017 |
17084097.73 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_cont_liner,Liner_s_m2 |
Tot_Mat_others |
0 |
359 |
Total_Mat_fl_grate_handrail_stairs |
Total cost of Material Floor grating (galvanized), Handrail, Stair treads in 2017 |
155313.36 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_fl_grate_handrail_stairs,Intern_tot_v_m3 |
Tot_Mat_others |
0 |
360 |
Total_Mat_painting |
Total cost of Material painting in 2017 |
957306.82 |
dollar |
tol_contaiment_ce_cost |
Unit_Mat_painting,Surf_paint_m2 |
Tot_Mat_others |
0 |
361 |
Sum_Labor_Cadweld |
Total cost of Labor Cadweld |
3280585.404 |
dollar |
sum_ce |
Total_Labor_Cadweld_Substr,Total_Labor_Cadweld_Superstr,Total_Labor_Cadweld_Dome,Total_Labor_Cadweld_Interior |
Tot_Labor_concr |
0 |
362 |
Sum_Labor_Concrete |
Total cost of Labor Concrete |
2535495.979 |
dollar |
sum_ce |
Total_Labor_Concrete_Substr,Total_Labor_Concrete_Superstr,Total_Labor_Concrete_Dome,Total_Labor_Concrete_Interior |
Tot_Labor_concr |
0 |
363 |
Sum_Labor_Constr_joints |
Total cost of Labor Constr joints |
320305.7975 |
dollar |
sum_ce |
Total_Labor_Constr_joints_Substr,Total_Labor_Constr_joints_Superstr,Total_Labor_Constr_joints_Dome,Total_Labor_Constr_joints_Interior |
Tot_Labor_concr |
0 |
364 |
Sum_Labor_Embedded_steel |
Total cost of Labor Embedded steel |
2423820.007 |
dollar |
sum_ce |
Total_Labor_Embedded_steel_Substr,Total_Labor_Embedded_steel_Superstr,Total_Labor_Embedded_steel_Dome,Total_Labor_Embedded_steel_Interior |
Tot_Labor_concr |
0 |
365 |
Sum_Labor_Formwork |
Total cost of Labor Formwork |
5164619.048 |
dollar |
sum_ce |
Total_Labor_Formwork_Substr,Total_Labor_Formwork_Superstr,Total_Labor_Formwork_Dome,Total_Labor_Formwork_Interior |
Tot_Labor_concr |
0 |
366 |
Sum_Labor_Maj_supp_embedments |
Total cost of Labor Maj supp embedments |
999574.0548 |
dollar |
sum_ce |
Total_Labor_Maj_supp_embedments_Interior |
Tot_Labor_concr |
0 |
367 |
Sum_Labor_Reinforc_steel |
Total cost of Labor Reinforc steel |
9459022.117 |
dollar |
sum_ce |
Total_Labor_Reinforc_steel_Substr,Total_Labor_Reinforc_steel_Superstr,Total_Labor_Reinforc_steel_Dome,Total_Labor_Reinforc_steel_Interior |
Tot_Labor_concr |
0 |
368 |
Sum_Labor_Rubbing_surfaces |
Total cost of Labor Rubbing surfaces |
305118.4026 |
dollar |
sum_ce |
Total_Labor_Rubbing_surfaces_Superstr,Total_Labor_Rubbing_surfaces_Dome,Total_Labor_Rubbing_surfaces_Interior |
Tot_Labor_concr |
0 |
369 |
Sum_Labor_Waterproofing |
Total cost of Labor Waterproofing |
25184.97376 |
dollar |
sum_ce |
Total_Labor_Waterproofing_Substr,Total_Labor_Waterproofing_Superstr,Total_Labor_Waterproofing_Dome |
Tot_Labor_concr |
0 |
370 |
Sum_Labor_Welded_wire_fabric |
Total cost of Labor Welded wire fabric |
21091.47636 |
dollar |
sum_ce |
Total_Labor_Welded_wire_fabric_Substr |
Tot_Labor_concr |
0 |
371 |
Sum_Mat_Cadweld |
Total cost of Material Cadweld |
1701340.49 |
dollar |
sum_ce |
Total_Mat_Cadweld_Substr,Total_Mat_Cadweld_Superstr,Total_Mat_Cadweld_Dome,Total_Mat_Cadweld_Interior |
Tot_Mat_concr |
0 |
372 |
Sum_Mat_Concrete |
Total cost of Material Concrete |
1747263.589 |
dollar |
sum_ce |
Total_Mat_Concrete_Substr,Total_Mat_Concrete_Superstr,Total_Mat_Concrete_Dome,Total_Mat_Concrete_Interior |
Tot_Mat_concr |
0 |
373 |
Sum_Mat_Constr_joints |
Total cost of Material Constr joints |
196460.25 |
dollar |
sum_ce |
Total_Mat_Constr_joints_Substr,Total_Mat_Constr_joints_Superstr,Total_Mat_Constr_joints_Dome,Total_Mat_Constr_joints_Interior |
Tot_Mat_concr |
0 |
374 |
Sum_Mat_Embedded_steel |
Total cost of Material Embedded steel |
1148307.391 |
dollar |
sum_ce |
Total_Mat_Embedded_steel_Substr,Total_Mat_Embedded_steel_Superstr,Total_Mat_Embedded_steel_Dome,Total_Mat_Embedded_steel_Interior |
Tot_Mat_concr |
0 |
375 |
Sum_Mat_Formwork |
Total cost of Material Formwork |
574341.9097 |
dollar |
sum_ce |
Total_Mat_Formwork_Substr,Total_Mat_Formwork_Superstr,Total_Mat_Formwork_Dome,Total_Mat_Formwork_Interior |
Tot_Mat_concr |
0 |
376 |
Sum_Mat_Maj_supp_embedments |
Total cost of Material Maj supp embedments |
1467166.11 |
dollar |
sum_ce |
Total_Mat_Maj_supp_embedments_Interior |
Tot_Mat_concr |
0 |
377 |
Sum_Mat_Reinforc_steel |
Total cost of Material Reinforc steel |
7957390.727 |
dollar |
sum_ce |
Total_Mat_Reinforc_steel_Substr,Total_Mat_Reinforc_steel_Superstr,Total_Mat_Reinforc_steel_Dome,Total_Mat_Reinforc_steel_Interior |
Tot_Mat_concr |
0 |
378 |
Sum_Mat_Rubbing_surfaces |
Total cost of Material Rubbing surfaces |
25051.63697 |
dollar |
sum_ce |
Total_Mat_Rubbing_surfaces_Superstr,Total_Mat_Rubbing_surfaces_Dome,Total_Mat_Rubbing_surfaces_Interior |
Tot_Mat_concr |
0 |
379 |
Sum_Mat_Waterproofing |
Total cost of Material Waterproofing |
13442.5802 |
dollar |
sum_ce |
Total_Mat_Waterproofing_Substr,Total_Mat_Waterproofing_Superstr,Total_Mat_Waterproofing_Dome |
Tot_Mat_concr |
0 |
380 |
Sum_Mat_Welded_wire_fabric |
Total cost of Material Welded wire fabric |
10870.38 |
dollar |
sum_ce |
Total_Mat_Welded_wire_fabric_Substr |
Tot_Mat_concr |
0 |
381 |
Tot_Labor_concr |
Total cost of labor of containment construction |
24534817.26 |
dollar |
sum_ce |
Sum_Labor_Cadweld,Sum_Labor_Concrete,Sum_Labor_Constr_joints,Sum_Labor_Embedded_steel,Sum_Labor_Formwork,Sum_Labor_Maj_supp_embedments,Sum_Labor_Reinforc_steel,Sum_Labor_Rubbing_surfaces,Sum_Labor_Waterproofing,Sum_Labor_Welded_wire_fabric |
Tot_Labor_containment |
0 |
382 |
Tot_Labor_equipment |
Total cost of labor of containment equipments |
1919453.529 |
dollar |
sum_ce |
Total_Labor_Lighting_Power,Total_Labor_Plumb_drains,Total_Labor_Special_HVAC,Total_Labor_other |
Tot_Labor_containment |
0 |
383 |
Tot_Labor_others |
Total cost of labor of other non-concrete related items |
17486505.19 |
dollar |
sum_ce |
Total_Labor_Misc_steel_frames,Total_Labor_React_cav_liner,Total_Labor_Struct_steel,Total_Labor_cont_liner,Total_Labor_fl_grate_handrail_stairs,Total_Labor_painting |
Tot_Labor_containment |
0 |
384 |
Tot_Mat_concr |
Total cost of material of containment construction |
14841635.07 |
dollar |
sum_ce |
Sum_Mat_Cadweld,Sum_Mat_Concrete,Sum_Mat_Constr_joints,Sum_Mat_Embedded_steel,Sum_Mat_Formwork,Sum_Mat_Maj_supp_embedments,Sum_Mat_Reinforc_steel,Sum_Mat_Rubbing_surfaces,Sum_Mat_Waterproofing,Sum_Mat_Welded_wire_fabric |
Tot_Mat_containment |
0 |
385 |
Tot_Mat_equipment |
Total cost of material of containment equipments |
1353108.842 |
dollar |
sum_ce |
Total_Mat_Lighting_Power,Total_Mat_Plumb_drains,Total_Mat_Special_HVAC,Total_Mat_other |
Tot_Mat_containment |
0 |
386 |
Tot_Mat_others |
Total cost of material of other non-concrete related items |
21289915.44 |
dollar |
sum_ce |
Total_Mat_Misc_steel_frames,Total_Mat_React_cav_liner,Total_Mat_Struct_steel,Total_Mat_cont_liner,Total_Mat_fl_grate_handrail_stairs,Total_Mat_painting |
Tot_Mat_containment |
0 |
387 |
Tot_Labor_containment |
Total cost of labor of containment |
43940775.98 |
dollar |
sum_ce |
Tot_Labor_concr,Tot_Labor_equipment,Tot_Labor_others |
NULL |
0 |
388 |
Tot_Mat_containment |
Total cost of material of containment |
37484659.35 |
dollar |
sum_ce |
Tot_Mat_concr,Tot_Mat_equipment,Tot_Mat_others |
NULL |
0 |